Hi,

Rebuilding my recently purchased Semi-D to improve built up and rework the old piping etc. TOtal duration planned 6 months. here are some initial pics:

Before:
https://picasaweb.google.com/10342305762555...feat=directlink

Just started works, Progress 1:
https://picasaweb.google.com/10342305762555...feat=directlink

My biggest challenge thus far is to level the ground floor. Today, the entrance hall and dining are saparated by 2 feet elevation. As i have yound kids, i am not keen with the elevation, so i am levelling the floors. The only thing is, instead of loosing out ceiling height on the groun floor, we have taken the approach to bring entire house level 0.5 as low as the foundation allows to level 0 (hall). So far, manage the bring the ground floor down by 1 foot..so have to raise hall by 1 foot....still will have a ceiling height of 10 feet once we have plaster ceiling!


Sky_cool86
post Dec 25 2011, 04:55 PM

New Member
*
Junior Member
30 posts

Joined: Dec 2011


Have fun for ur journey :-)
kelvyn
post Dec 25 2011, 06:56 PM

Look at all my stars!!
*******
Senior Member
3,173 posts

Joined: May 2007
It is really a challenge to be able to bring down the existing ground level. Having to overcome the existing underground services, ground beams and footings.

weikee
post Dec 25 2011, 09:44 PM

10k Club
********
All Stars
12,019 posts

Joined: Jan 2003
Nice project.
phoenix69
post Dec 25 2011, 10:37 PM

Regular
******
Senior Member
1,836 posts

Joined: Sep 2007


Wow this looks like you are tearing down the whole house and building it up again. .... Maybe the cost will be cheaper and the process faster if you done this instead..
zheilwane
post Dec 25 2011, 10:44 PM

Look at all my stars!!
*******
Senior Member
4,184 posts

Joined: Jan 2008
From: Builders Hardware Enterprise 0362572412
Seems like u r doing some major renovation there.. Good luck and happy renovating smile.gif
TSgoks
post Dec 27 2011, 09:17 AM

Getting Started
**
Junior Member
79 posts

Joined: Aug 2009
Thanks Guys. DBKL is a little fussy when it comes to tearing it all down. The challenge in flattening the ground floor is the size of support beams on the ground. You cant cut it off completely...so you can go as low as shaving half the beams off but no more....my goal was to lower the house 2 feet...what we achieved was only 1 feet.so i had to bring my hall up by 1 feet to meet level!


I have updated the pictures on the before and after house plans:
https://picasaweb.google.com/10342305762555...feat=directlink


tiensong
post Dec 27 2011, 11:28 AM

Look at all my stars!!
*******
Senior Member
2,237 posts

Joined: Jul 2011
may I know how much you purchase the house and the total land area? thanks
leeyung
post Dec 27 2011, 11:30 AM

1st LYN Pioneer Genuine Marimo Seller
*****
Senior Member
885 posts

Joined: Sep 2008

woho~ major reno there, $$
TSgoks
post Dec 27 2011, 02:11 PM

Getting Started
**
Junior Member
79 posts

Joined: Aug 2009
Land area 5200 sqft, purchased 1.2M back in Jan this year...actually bought it in december 2010.

 