hi there, i just wondering how to find out the project phase 3a is late to hand over the keys?how do we justify it?from the s and p we signed or from the date we booked the unit?pls advised.

thanks
Almondbox
post Aug 26 2012, 03:56 PM

New Member
*
Junior Member
9 posts

Joined: May 2012
Hi phase 3a owner..

Currently I received vacant possession for the property of taman putra impiana phase 3a and there is a late interest charges up to 7k. Does anyone have this issue?? The property are ready to collect keys as well .
Almondbox
post Aug 27 2012, 11:15 AM

New Member
*
Junior Member
9 posts

Joined: May 2012
QUOTE(james3674 @ Aug 26 2012, 10:28 PM)
Hi, Are you received the letter from Developer the Phase 3A property is ready to collect key? Why i still not receive the letter yet? How abt other owner?
*
yes i did received the letter but dont worry i think the u all can get it soon.

Almondbox
post Aug 27 2012, 05:19 PM

New Member
*
Junior Member
9 posts

Joined: May 2012
congrats to all new residents in taman putra impiana Phase 3A rclxms.gif ..

Btw do u guys know how to calculate the late hand over keys interest?is it from the s n p date?
Almondbox
post Aug 29 2012, 03:30 PM

New Member
*
Junior Member
9 posts

Joined: May 2012
QUOTE(tehaikseong @ Aug 28 2012, 01:02 PM)
my bank has not received the letter from developer to pay for the last progress payment, seem like i cannot collect my key on next week  cry.gif
*
u have to let ur bank know.like me my bank also didnt received any letter from developer until i call them.the bank now start preparing the remaining balance to them.
Almondbox
post Aug 30 2012, 04:41 PM

New Member
*
Junior Member
9 posts

Joined: May 2012
QUOTE(james3674 @ Aug 29 2012, 03:54 PM)
I had called my bank to check this morning, the bank officer inform me that the final release amount already credit to developer account. The official letter and cheque already send to lawyer side.


Added on August 30, 2012, 2:23 pmHi Phase 3A owner, any of you encounter the late payment charge by developer? I call both party financier bank and loan lawyer, all of them also escape the issue. Too bad. Is it you all will going to pay the late charge?
*
I did encounter the issue but i keep all my receipt from my bank and developer and they manage to waive the interest charges for me cause the issue is not come from me here.so i would suggest u find back the receipt and check which progressive payment is delay.then only u can talk to your bank, lawyer and developer about this issue.perhaps u can ask your bank and lawyer to provide u the chronology of the event to rectify the payment.i hope this will help u .
Almondbox
post Sep 3 2012, 09:08 AM

New Member
*
Junior Member
9 posts

Joined: May 2012
QUOTE(james3674 @ Aug 30 2012, 05:04 PM)
Tq for your advise. I had call the loan lawyer to find out why they delay release my loan. Hope they will come back to me asap. May i know which party problem due to your late payment charge?  Lawyer, developer / bank?
*
The issue come from the developer. My bank already give the payment and they didn't update it.
Almondbox
post Nov 13 2012, 05:10 PM

New Member
*
Junior Member
9 posts

Joined: May 2012
Phase 3A owner,Does anyone's face roof leaking or water tank leaking at the 2nd floor bedroom?i can see some water stain on top of the ceiling.how to ask them to check?

 