 Koi Kinrara

views
     
JRZ
post Apr 24 2011, 11:00 PM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2010
From: Selangor


QUOTE(Ordinary83 @ Apr 24 2011, 10:33 PM)
How was the progress now? Anyone know ?
*
23/04/2011 Site Progress

Block C reaches C-07
Block D reaches D-03

Attached Image
JRZ
post Apr 25 2011, 09:27 PM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2010
From: Selangor


QUOTE(Ordinary83 @ Apr 25 2011, 08:24 PM)
JRZ , Thanks! Hwo come Block C is much more faster than Block D. Just curious hehe !! tongue.gif
*
Just difference of 4 floors, by end of 2012 both blocks will be completed.
JRZ
post Apr 28 2011, 10:58 AM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2010
From: Selangor


QUOTE(Ordinary83 @ Apr 27 2011, 07:19 PM)
Oh ya.. Did you anyone of you able to join the Koi Kinrara Forum ? I was registered myself since few months ago.. still havent receive confirmation email . Tq
*
u should follow up with the administrator.

This post has been edited by JRZ: Apr 28 2011, 11:00 AM
JRZ
post May 10 2011, 05:54 PM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2010
From: Selangor


QUOTE(siaww @ May 9 2011, 06:05 PM)
No worry the scrap metal operator sure will move out later. That factory area will redevelop in future..
*
numerous complaints been launched to MPSJ by koi residents since mid 2010 but their operation still prevails.
keeping our fingers crossed.

This post has been edited by JRZ: May 10 2011, 05:57 PM
JRZ
post Jun 10 2011, 01:50 PM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2010
From: Selangor


09/06/2011 Site Progress

Block C Level-10
Block D Level-03

This post has been edited by JRZ: Jul 25 2011, 11:28 PM
JRZ
post Jul 25 2011, 11:27 PM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2010
From: Selangor


25/07/2011 Site Progress

Block C Level-12
Block D Level-03
JRZ
post Aug 30 2011, 12:53 AM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2010
From: Selangor


28/08/2011 Site Progress

Block C Level-13
Block D Level-3A
JRZ
post Sep 20 2011, 03:37 PM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2010
From: Selangor


QUOTE(vincent kee @ Sep 20 2011, 01:37 PM)
are them intent to handover block c first, than only start to do block d?
*
Block C & D is part of Phase 2 so handover is both at the same time just like Phase 1 (Block A & B)
JRZ
post Sep 21 2011, 02:17 PM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2010
From: Selangor


QUOTE(vincent kee @ Sep 21 2011, 02:06 PM)
but yet still no progress at block d,m really super snailing slow...
*
this are the few reasons given by the management for the slow progress of Block D:-

1) Delay in arrival of purchased raw materials
2) Foundation work and frame structure is more complex because of the sky garden weight balance requirements
3) Unsold 18 units (1,405sf)
JRZ
post Sep 27 2011, 01:31 PM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2010
From: Selangor


QUOTE(vincent kee @ Sep 26 2011, 08:50 PM)
reason not acceptable cos,
1) block c and d is using the same materials, how come block c got, but block d no? those materials for structure just rebar, formwork and concrete, no other thing. rebar is fabrication at site. the delivery rebar is standard size only, they just cut n bend to required shape and lenght.
2) block d already up to 3rd floor, means the foundation already done, so no loading issue should have at this status.
3) 18 units just 3.6% unsold only, that should be very good already. they sure gain money if left only 18 units.
*
typical of developer to provide lame excuses.
JRZ
post Oct 12 2011, 03:41 PM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2010
From: Selangor


QUOTE(jasmineh2y @ Oct 4 2011, 03:34 PM)
anymore news about the development progress?
*
12/10/2011 Site Progress

Block C Level-15
Block D Level-06
JRZ
post Oct 31 2011, 02:11 AM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2010
From: Selangor


30/10/2011 Site Progress

Block C Level-16
Block D Level-08
JRZ
post Nov 23 2011, 02:05 PM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2010
From: Selangor


23/11/2011 Site Progress

Block C Level-17
Block D Level-09
JRZ
post Aug 26 2013, 11:12 PM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2010
From: Selangor


http://mykampung.sinchew.com.my/node/248322

Attached Image

Koi Kinrara Puchong apartment with scrap vendors reached a consensus and signed the memorandum of understanding, ending a four-year dispute due to environmental and noise pollution.

 