QUOTE(Ordinary83 @ Apr 24 2011, 10:33 PM)
23/04/2011 Site Progress Block C reaches C-07
Block D reaches D-03
Koi Kinrara
|
|
Apr 24 2011, 11:00 PM
Return to original view | Post
#1
|
![]() ![]()
Junior Member
202 posts Joined: Jan 2010 From: Selangor |
|
|
|
|
|
|
Apr 25 2011, 09:27 PM
Return to original view | Post
#2
|
![]() ![]()
Junior Member
202 posts Joined: Jan 2010 From: Selangor |
|
|
|
Apr 28 2011, 10:58 AM
Return to original view | Post
#3
|
![]() ![]()
Junior Member
202 posts Joined: Jan 2010 From: Selangor |
|
|
|
May 10 2011, 05:54 PM
Return to original view | Post
#4
|
![]() ![]()
Junior Member
202 posts Joined: Jan 2010 From: Selangor |
QUOTE(siaww @ May 9 2011, 06:05 PM) No worry the scrap metal operator sure will move out later. That factory area will redevelop in future.. numerous complaints been launched to MPSJ by koi residents since mid 2010 but their operation still prevails.keeping our fingers crossed. This post has been edited by JRZ: May 10 2011, 05:57 PM |
|
|
Jun 10 2011, 01:50 PM
Return to original view | Post
#5
|
![]() ![]()
Junior Member
202 posts Joined: Jan 2010 From: Selangor |
09/06/2011 Site Progress
Block C Level-10 Block D Level-03 This post has been edited by JRZ: Jul 25 2011, 11:28 PM |
|
|
Jul 25 2011, 11:27 PM
Return to original view | Post
#6
|
![]() ![]()
Junior Member
202 posts Joined: Jan 2010 From: Selangor |
25/07/2011 Site Progress
Block C Level-12 Block D Level-03 |
|
|
|
|
|
Aug 30 2011, 12:53 AM
Return to original view | Post
#7
|
![]() ![]()
Junior Member
202 posts Joined: Jan 2010 From: Selangor |
28/08/2011 Site Progress
Block C Level-13 Block D Level-3A |
|
|
Sep 20 2011, 03:37 PM
Return to original view | Post
#8
|
![]() ![]()
Junior Member
202 posts Joined: Jan 2010 From: Selangor |
|
|
|
Sep 21 2011, 02:17 PM
Return to original view | Post
#9
|
![]() ![]()
Junior Member
202 posts Joined: Jan 2010 From: Selangor |
QUOTE(vincent kee @ Sep 21 2011, 02:06 PM) this are the few reasons given by the management for the slow progress of Block D:-1) Delay in arrival of purchased raw materials 2) Foundation work and frame structure is more complex because of the sky garden weight balance requirements 3) Unsold 18 units (1,405sf) |
|
|
Sep 27 2011, 01:31 PM
Return to original view | Post
#10
|
![]() ![]()
Junior Member
202 posts Joined: Jan 2010 From: Selangor |
QUOTE(vincent kee @ Sep 26 2011, 08:50 PM) reason not acceptable cos, typical of developer to provide lame excuses.1) block c and d is using the same materials, how come block c got, but block d no? those materials for structure just rebar, formwork and concrete, no other thing. rebar is fabrication at site. the delivery rebar is standard size only, they just cut n bend to required shape and lenght. 2) block d already up to 3rd floor, means the foundation already done, so no loading issue should have at this status. 3) 18 units just 3.6% unsold only, that should be very good already. they sure gain money if left only 18 units. |
|
|
Oct 12 2011, 03:41 PM
Return to original view | Post
#11
|
![]() ![]()
Junior Member
202 posts Joined: Jan 2010 From: Selangor |
|
|
|
Oct 31 2011, 02:11 AM
Return to original view | Post
#12
|
![]() ![]()
Junior Member
202 posts Joined: Jan 2010 From: Selangor |
30/10/2011 Site Progress
Block C Level-16 Block D Level-08 |
|
|
Nov 23 2011, 02:05 PM
Return to original view | Post
#13
|
![]() ![]()
Junior Member
202 posts Joined: Jan 2010 From: Selangor |
23/11/2011 Site Progress
Block C Level-17 Block D Level-09 |
|
|
Aug 26 2013, 11:12 PM
Return to original view | Post
#14
|
![]() ![]()
Junior Member
202 posts Joined: Jan 2010 From: Selangor |
http://mykampung.sinchew.com.my/node/248322
Koi Kinrara Puchong apartment with scrap vendors reached a consensus and signed the memorandum of understanding, ending a four-year dispute due to environmental and noise pollution. |