 Taipan Group of Companies - Residency@Park51, Have you heard of this developer?

views
     
khyuen
post Apr 25 2012, 09:11 AM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
Time to write in to Syabas and complain. Any email address that we can sent to?
I only found this email address on their website.

webmaster@syabas.com.my
khyuen
post Apr 25 2012, 02:11 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
QUOTE(doomdoom @ Apr 25 2012, 01:34 PM)
Yes i also dun wan the clubhouse and swimming pool failicties just keep delaying like this...but refering to the last email that Andy frm developer that sent to me..the swimming pool most probably will complete and open for use after block C complete for safety purpose..and block C might only complete in the mid of year 2014...this is a very bad for us...
Block D will be handed over first, A, B and C will probably be handed together with full facilities available by then. We can prepare the swimming pool for residence to use, but if anything happens, do the residence bare the consequences or developer? You also have to understand safety measures and protocols. The main question is, who will be responsible when something happens? We do see and discuss issues but rest assured, it's always for the best interest of our purchasers.
Block D was completed late last year as i have mentioned before. Just that certain minor issues in regards to insufficient of water meters from Syabas prevented inspection from other local departments such as Tenaga, Bomba, etc. But all inspection has been done and the CF will be out in a week or two time. Hopefully you and other purchasers will be able to get your keys next month.

*
Doom,when was this email reply to you?
khyuen
post Apr 27 2012, 02:01 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
Great! count me in too! we should fight for our compensation.
khyuen
post May 2 2012, 11:26 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
I am one of the early purchasers which SNP 3rd dec 2009, as of today they still have 25% to draw down from my bank loan.

I hope to get keys by middle of the month. What's the next step of action?

khyuen
post May 7 2012, 05:15 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
Just past by Park 51, seems no progress on the club house. I doubt they can handover the keys this month.


Added on May 7, 2012, 5:16 pmEven though it's not related to our condo, i don't see any guard house or auto access gate build on the entrance.

This post has been edited by khyuen: May 7 2012, 05:16 PM
khyuen
post May 9 2012, 09:11 AM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
it's already the 2nd week of May, i really hope they can deliver the keys within the next 3 weeks.
khyuen
post May 9 2012, 04:35 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
sent an email today to taipan, awaiting an email reply.
khyuen
post May 11 2012, 03:59 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ

My email to taipan 2 days ago.

May i know the status as of today. When can we take vacant possessions and the hand over of keys?


Reply from Taipan today.

Should be soon, waiting for last approval letter from Syabas side.
khyuen
post May 11 2012, 10:50 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ

keep me in the loop too.

khyuen@yahoo.com


khyuen
post May 23 2012, 09:09 AM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
Syabas has not reverted too in the email.
khyuen
post Jun 3 2012, 11:36 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
Today is Sunday, another week to go.... finger's cross that all of us will get the keys before 15th of June.


khyuen
post Jun 5 2012, 11:04 AM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
I went to see the front entrance on Sunday. There is no barrier's for access gate on both entrance and exit. I believe the access barrier will be in the parking lot.

No doubt there's still plenty of work to do on the club house, if they focus on it, shouldn't have problem to complete it by December.

For the swimming pool and block C, i went to visit the temple opposite the school, still not completed yet. So for the temple relocation, i don't think they can move out in July.
khyuen
post Jun 5 2012, 01:16 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
This is only assumption on my personal view. There are some condo/apartment where they allow you to drive in. There will be another guard house in the parking lot.

Maybe someone can ask the developer on the access barrier.
khyuen
post Jun 5 2012, 05:19 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
QUOTE(doomdoom @ Jun 5 2012, 05:10 PM)
I think this developer is not tat bad...at least this developer wait for CF and VP together...

i know some developer issue VP 1st without waiting for CF...so buyers can get the key but cant move in...just can do some renovation...and the defect warranty start to count when upon VP....


Added on June 5, 2012, 5:15 pm
not need keep guessing in this forum..i already emailed to developer ask about this...cc u all inside the mail...u may keep questioning or calling develoepr to ask about this...
*
it's no longer called CF anymore....they have change it to Certificate of Completion and Compliance. So it's CCC instead of CF.

Yes some developer hand over the keys to owners first, but if you have some owners who did some major renovation to the unit, The CCC will not approve it.
khyuen
post Jun 6 2012, 09:43 AM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
Thanks for uploading the photos. Now awaiting for Syabas approval and Taipan to hand over the keys.
khyuen
post Jun 7 2012, 09:29 AM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
I have receiving so many property agents call and sms lately, not sure whether you guys get those calls and smses too?
khyuen
post Jun 8 2012, 05:23 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
so it's already friday.....yet to hear from developer or syabas.
khyuen
post Jun 11 2012, 10:43 AM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
Ting & Hong has sent emails to taipan, seems that the developers are not replying email and neither we are getting any updates on Syabas.
khyuen
post Jun 11 2012, 02:38 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
Great. We can move in to Park 51 very soon.

I passed by yesterday, seems like the entrance yet to install any access barriers.
khyuen
post Jun 13 2012, 01:54 PM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2005
From: PJ
nothing wrong on 390 psf. They are just trying their luck. I had an offer for 410 psf. Not selling. Will be moving in soon.....