QUOTE(ozak @ May 14 2018, 12:02 PM)
No problem.
It is not like how many power point. It is more how you balance the load.
For example, if you wired up 3 aircon in 1P (red), that is not balance load.
If you wired each aircon on each 1P, that is balance load.
So if you put 5 power points on each phase, But you plug in your mining rig on the yellow, no use right ?
Hi Sir,It is not like how many power point. It is more how you balance the load.
For example, if you wired up 3 aircon in 1P (red), that is not balance load.
If you wired each aircon on each 1P, that is balance load.
So if you put 5 power points on each phase, But you plug in your mining rig on the yellow, no use right ?
Hope you can help me on this matter.
From the tnb meter (outside) to switchboard (inside), the underground armor cable should be one piece right?
cause i found out the contractor using 2 or 3 cables connect together. If you need to see photo, I can pm you.
is this the standard practice?