Hi all,
I got my original contractor to do my 3 Phase wiring and this is one thing that i think is super high price ><. Can someone tell me is this really what it is suppose to be!? I have checked with 2 other person and they paid like RM2k till 3k only for the 3Phase total but this could be because their house is newer then mine that is why its cheaper. My house is about 30years old.
TMB fee + deposit
RM 2250 (still variable price depending on TNB quote)
New DB + 3Phase MCB + 1x40A 300mA 4P RCD + 27x10/20A 1P MCB + PVC housing + internal looping wiring and busbar + metal clad metering panel + 3x60A cut-out fuse and neutral link + 40ft underground PVC cable PVC pipe with electrical pits
RM3223
Application for TNB 63A 3-phase supply + Borang A endorsed single line diagram, endorsed Borang G & H, testing and commissioning and processing charge.
RM965
Total out RM 6438
Renovations 3-phase wiring