Just pointing out a 20 day estimate is not impossible, but really depends on the scope of work.
You yourself just gave an example of a 3 day job for which you estimated 1 week. Frankly I would do the same to account for unforeseen things happening halfway.
It is not impossible, depending on what they are promising.
if its outdoor, budget for weather. and also delays in material worker availability, etcYou yourself just gave an example of a 3 day job for which you estimated 1 week. Frankly I would do the same to account for unforeseen things happening halfway.
It is not impossible, depending on what they are promising.