QUOTE(RigerZ @ Mar 7 2025, 07:49 PM)
https://www.thestar.com.my/news/nation/2025...ning-on-sept-30
This says the service will start on 30th Sept and the project is 98% complete
https://www.thestar.com.my/business/busines...247bil-lrt3-job
Then this says MRCB secured the contract to complete another remaining 5 stations within 4 years
How is the project 98% done when there are 5 stations remaining, and how do train services run when station constructions are ongoing... Am I missing something? :confused:
The 5 stations used to be provisional stations during LGE time, and then reinstate recently along with additional train sets... The main line will run w/o stopping at the stations that are under construction. It is possibleThis says the service will start on 30th Sept and the project is 98% complete
https://www.thestar.com.my/business/busines...247bil-lrt3-job
Then this says MRCB secured the contract to complete another remaining 5 stations within 4 years
How is the project 98% done when there are 5 stations remaining, and how do train services run when station constructions are ongoing... Am I missing something? :confused:
This post has been edited by akira87: Mar 7 2025, 08:14 PM
Mar 7 2025, 08:13 PM