Welcome Guest ( Log In | Register )

Outline · [ Standard ] · Linear+

 Floor plan and Home Reno, Bukit Serdang 5

views
     
TSlowprofiledude P
post Feb 6 2023, 11:04 PM, updated 3y ago

New Member
*
Probation
7 posts

Joined: Feb 2023
Hi All,

Not sure anyone willing to share their detailed floor plan for Bukit Serdang 5/3 area?

I have recently bought a landed property there.
Would like to apply for renovation approval but there is no floor plan from the previous owner.

Have tried to called MPSJ and they told me that they do not have any record for the plan and developer sad sad.gif .
I have also googled but there is no information on who is the developer.

Appreciate if any member around the area mind to share information on developer or the floor plan with me ?

Thanks a lot !
TSlowprofiledude P
post Feb 7 2023, 12:13 PM

New Member
*
Probation
7 posts

Joined: Feb 2023
QUOTE(StupidGuyPlayComp @ Feb 7 2023, 11:55 AM)
i think that house aged 30 years or above, owner hardly have floor plan on hand
*
Yes, the house is old community. They are not G&G as well.
And my neighbor bought it from previous owner so do not have the floor plan.
Tried to get help from my lawyer but they could not help too.
That is why it is making the search so difficult. sad.gif
TSlowprofiledude P
post Feb 10 2023, 12:23 AM

New Member
*
Probation
7 posts

Joined: Feb 2023
Thanks for your reply. It does clarify the alternative.

However , are you able to advise how much will it cost for the drafting and also submission usually?
TSlowprofiledude P
post Feb 10 2023, 12:25 AM

New Member
*
Probation
7 posts

Joined: Feb 2023
QUOTE(ArchId @ Feb 8 2023, 11:33 AM)
Oh, one issue if buying a subsale landed house is when the previous owner doing illegal exterior renovation that
may exceed the building setback line....which will be troublesome when you want to apply for a proper new renovation extension
works...if changes on the interior of a house is still passable... as long not affecting the building façade/ outlook

cheers mate,
izwan
www.archidstudio.com
*
TSlowprofiledude P
post Feb 11 2023, 11:21 PM

New Member
*
Probation
7 posts

Joined: Feb 2023
QUOTE(ArchId @ Feb 10 2023, 06:55 AM)
Good day mate

Pricing depends on which type of house you purchased

A) terrace , semi-d , bungalow ?
B) single or double / triple storey house
C) purpose idea of extension - only on ground floor ? Or both upper floor as well …. If only ground floor does not required structure engineer P.E endorsement complete with structure design , and structure design calculation and reports .. which basically will add additional cost .
D) if got original plan / S&P plan - we could just scan and trace it - reduce of pricing compared to go and do measured drawings.
E) got CF cert with you ? If don’t have … then need to do cf search at majlis / council … if no result from them, then have to write a declaration and proceed with the commissioner of oath … got sometimes need to go to court / mahkamah kecil to declare in front of the judge … depends on situation…
F) got original land grant with you ? If not need to go to pejabat tanah (land office ) and search for the house land grant

All these needed to do submission… so if you got all these , then pricing would be cheaper ….if not …. Just standby ranging 5.5-7K
( not including payment directly to council ya ) example
1) payment of processing plan
2) payment of rental  row2 bin from their panel ( few trips only)
3) deposit payment ( WAng cagaran )

All in standby 9-10k …..

This is the proper way… got short cut way which I don’t ethically advise…
Hope that answer you question

Cheers mate
Izwan
Www.archidstudio.com
*
Thanks for the detailed explanation. I understand that too.
Hope you don't mind for another question, usually how long does the whole process goes by ?
From draft of plan to approval from authority?

TSlowprofiledude P
post Feb 13 2023, 04:29 PM

New Member
*
Probation
7 posts

Joined: Feb 2023
QUOTE(ArchId @ Feb 12 2023, 12:21 AM)
Excluding site measurement only Drafting  - 1.5 weeks if purely architecture drawings .. if required structure need to wait since the structure Engr need to overlap drawings taken from architecture drawings: add another 1 - 1.5week…

Once complete and if everything comply to the officer requirements then they will process 14days - 30days (working days) …. But normally always got some comments from the officer .. depending on which officer .. some of them can be reasonable , some don’t and insist to follow his/her comments…. Normally what we do is print draft copy and set an apointment with the officer for his/her initial comments… reduce the time for drawing amendments…

Total about 1.5month- 2 month

Hope this helps
Cheers mate
Izwan
Www.archidstudio.com
*
Thanks Mate. This clarifies ! biggrin.gif

 

Change to:
| Lo-Fi Version
0.0164sec    0.25    6 queries    GZIP Disabled
Time is now: 4th December 2025 - 02:54 AM