QUOTE(kazekage_09 @ Dec 6 2020, 01:59 PM)
Hi all looking for advice on my quotation as per below:
Lander, Hacking, Fencing Works
===================
1. Brick wall fencing 195ft (L) x 5 ft (H), concrete ground beam, 20 unit concrete pillars, install capping cornice and plaster finish. RM26500
400 per m run seems a reasonable contractor price but on the high side for me personally. Depends on site difficulty as well. no drainage for the wall? subsoil pipe?
2. Hacking and demolish existing fence and clearing work RM300
This one consider day wage say 120 per person. Sum too small to haggle actually
3. Clearing soil, install 4" PVC 50ft (L) drain pipe & clear rubbish work charge RM1000
again hard to haggle, btw 600-800.
4. Lander 4" concrete 500sgf on back yard, install BRC A8 and plaster finish 7000
approx 50m2@140 seems reasonable
Slab Leaking Works
=============
1. For checking and repair slab family hall, seal cement, washing clean & use boscoseal water proofing install on slab area 3500
Hard to comment as price might include future rectification works
PU Foam Roof Works
=============
1. Supply and install 9.5ft (L) x 32ft (W) and 9.5ft (L) x 18 ft9W) total 475sqf PU Metal Roof, PU Foam roof on back yard, bracket use 2"x4", 2"x3" hollow iron bar + 3"x3" hollow iron pillar x 5 unit & paint finish Rm13500
not too familiar with price but prob double of your concrete slab price. hollow section thickness 1mm or less?
S. Steel Drain Gutter Works
=================
1 Install 50ft (L) stainless steel drain gutter RM3200
wow
Painting Works
=========
1. Painting work for new build up fencing 200ft(L) renocation area, using nippon paint sealer and weather bond color paint finish RM4000
a bit high
Rubbish Charge
==========
1. Rubbish and transport charge RM600
reasonable
Total RM59600
Is this reasonable? Or pricey?
Thank you!
bear in mind i am picking item by item. sometimes we front load or backload items to cover unforeseen items and the total sum to be looked at as a whole. not fair to pick on item by item. dont just look at final price. paying a bit more usually saves a lot of future hassle. know the contractor reputation or current work in progress. might consider a retention sum if amount large to make sure they make good any future defectLander, Hacking, Fencing Works
===================
1. Brick wall fencing 195ft (L) x 5 ft (H), concrete ground beam, 20 unit concrete pillars, install capping cornice and plaster finish. RM26500
400 per m run seems a reasonable contractor price but on the high side for me personally. Depends on site difficulty as well. no drainage for the wall? subsoil pipe?
2. Hacking and demolish existing fence and clearing work RM300
This one consider day wage say 120 per person. Sum too small to haggle actually
3. Clearing soil, install 4" PVC 50ft (L) drain pipe & clear rubbish work charge RM1000
again hard to haggle, btw 600-800.
4. Lander 4" concrete 500sgf on back yard, install BRC A8 and plaster finish 7000
approx 50m2@140 seems reasonable
Slab Leaking Works
=============
1. For checking and repair slab family hall, seal cement, washing clean & use boscoseal water proofing install on slab area 3500
Hard to comment as price might include future rectification works
PU Foam Roof Works
=============
1. Supply and install 9.5ft (L) x 32ft (W) and 9.5ft (L) x 18 ft9W) total 475sqf PU Metal Roof, PU Foam roof on back yard, bracket use 2"x4", 2"x3" hollow iron bar + 3"x3" hollow iron pillar x 5 unit & paint finish Rm13500
not too familiar with price but prob double of your concrete slab price. hollow section thickness 1mm or less?
S. Steel Drain Gutter Works
=================
1 Install 50ft (L) stainless steel drain gutter RM3200
wow
Painting Works
=========
1. Painting work for new build up fencing 200ft(L) renocation area, using nippon paint sealer and weather bond color paint finish RM4000
a bit high
Rubbish Charge
==========
1. Rubbish and transport charge RM600
reasonable
Total RM59600
Is this reasonable? Or pricey?
Thank you!