QUOTE(Twenty-Fifth Baam @ May 29 2019, 05:53 PM)
My house VP-ed 2 months ago and I just got my keys last week, but it is missing the TNB meter. Is that correct? Can they give out the keys without the TNB meter?
Is there anything that I can do to get it done faster? Other than chasing them to install the TNB meter faster?
Bloody developer told me need 1 month to install 1 bloody TNB meter, wtf?
Under standard Schedule H, Developer only need to make sure that the electrical connection is ready to tap into ur unit.Is there anything that I can do to get it done faster? Other than chasing them to install the TNB meter faster?
Bloody developer told me need 1 month to install 1 bloody TNB meter, wtf?
The installation of TNB meter is not under their scope but service provider.
You should get a copy of ur meter application form from the developer and chase TNB for the installation.