ulala2
post May 30 2019, 01:04 PM

Getting Started
**
Junior Member
245 posts

Joined: Jul 2007
QUOTE(Twenty-Fifth Baam @ May 29 2019, 05:53 PM)
My house VP-ed 2 months ago and I just got my keys last week, but it is missing the TNB meter. Is that correct? Can they give out the keys without the TNB meter?

Is there anything that I can do to get it done faster? Other than chasing them to install the TNB meter faster?

Bloody developer told me need 1 month to install 1 bloody TNB meter, wtf?
*
Under standard Schedule H, Developer only need to make sure that the electrical connection is ready to tap into ur unit.
The installation of TNB meter is not under their scope but service provider.

You should get a copy of ur meter application form from the developer and chase TNB for the installation.
ulala2
post May 31 2019, 12:13 PM

Getting Started
**
Junior Member
245 posts

Joined: Jul 2007
QUOTE(Twenty-Fifth Baam @ May 30 2019, 03:14 PM)
but the problem is, they gave me a form to fill it, then take it back... they said will "help" me do the application

they took rm1k+ for the tnb/electrical/whatever shit deposit from me also
*
This is normal when the development still under construction.
In some case, TNB need to verify the cabling and with the present of the owner when they install the meter. And also request owner to make appointment with TNB for that.

Better to get a copy of the application from Developer, then go directly to TNB to ask for the status.
This will be the faster way.
TQ

 