QUOTE(sovietmah @ Jun 17 2024, 04:22 PM)
Hi, I am at subang jaya, i wanted to install solar panel up to 9KW, so I have to change to 3 phases.
Electrician is quoting me Rm5K include helping me to install the 3 phases meter, extend the dbbox, apply tnb which require 2 months waiting max. Rm5k didnt include rm300 connection changes by tnb and didnt include security deposit.
My house is the last house in the section and has 4 tnb cables so electrician said doesn't require tnb to pull new cable from the pole.
Any idea if the price is reasonable?
Yes that is about right price.Electrician is quoting me Rm5K include helping me to install the 3 phases meter, extend the dbbox, apply tnb which require 2 months waiting max. Rm5k didnt include rm300 connection changes by tnb and didnt include security deposit.
My house is the last house in the section and has 4 tnb cables so electrician said doesn't require tnb to pull new cable from the pole.
Any idea if the price is reasonable?
Jun 20 2024, 04:08 PM

Quote
0.0156sec
0.53
6 queries
GZIP Disabled