Hi, i'm newbie in this thread.
Just want to know any status about K5 MOPU? Out of sudden silent, and checked with RNZ they are also no idea......
Oil & Gas Careers V12 - Upstream & Downstream, Market still slump, slow, snail pace...
Oil & Gas Careers V12 - Upstream & Downstream, Market still slump, slow, snail pace...
|
|
Oct 17 2019, 06:41 PM
Return to original view | Post
#1
|
![]()
Newbie
40 posts Joined: Aug 2009 |
Hi, i'm newbie in this thread.
Just want to know any status about K5 MOPU? Out of sudden silent, and checked with RNZ they are also no idea...... |
|
|
|
|
|
Oct 17 2019, 07:26 PM
Return to original view | Post
#2
|
![]()
Newbie
40 posts Joined: Aug 2009 |
|
|
|
Oct 31 2019, 12:14 PM
Return to original view | Post
#3
|
![]()
Newbie
40 posts Joined: Aug 2009 |
|
|
|
Oct 31 2019, 02:41 PM
Return to original view | Post
#4
|
![]()
Newbie
40 posts Joined: Aug 2009 |
Check with all master/sifu/guru here about Shell Rosemary project.
Had a chit-chat with colleague, he said this project put on hold or KIV now, due to some dispute between Shell and Petronas. For what i know, this project is under going pre-feed by Ranhill WorleyParson, seems this project quite sure will roll out. Any master/sifu/guru can validate the info above? TQVM. |
|
|
Oct 31 2019, 06:54 PM
Return to original view | Post
#5
|
![]()
Newbie
40 posts Joined: Aug 2009 |
|
|
|
Nov 4 2019, 09:59 AM
Return to original view | Post
#6
|
![]()
Newbie
40 posts Joined: Aug 2009 |
|
|
|
|
|
|
Nov 4 2019, 10:06 AM
Return to original view | Post
#7
|
![]()
Newbie
40 posts Joined: Aug 2009 |
|
|
|
Nov 7 2019, 04:23 PM
Return to original view | Post
#8
|
![]()
Newbie
40 posts Joined: Aug 2009 |
Actually here can discuss onshore/down stream jobs? Kerteh there many activities are coming.
|
|
|
Nov 7 2019, 04:53 PM
Return to original view | Post
#9
|
![]()
Newbie
40 posts Joined: Aug 2009 |
|
|
|
Nov 7 2019, 06:01 PM
Return to original view | Post
#10
|
![]()
Newbie
40 posts Joined: Aug 2009 |
|
|
|
Nov 11 2019, 11:50 AM
Return to original view | Post
#11
|
![]()
Newbie
40 posts Joined: Aug 2009 |
|
|
|
Nov 28 2019, 05:20 PM
Return to original view | Post
#12
|
![]()
Newbie
40 posts Joined: Aug 2009 |
QUOTE(Maverick85 @ Nov 28 2019, 04:01 PM) Tenders going on for EPCIC of 2 wellhead Platforms, Subsea Pipelines and Host Tie-ins Works for JDA Block B-17 Field Development Project (Phase 5), for CPOC, consisting of 2xjackets and 2xtopsides, namely Muda G & Tapi B. There is high chance that this would be fabricated in Malaysia, as Phase 4 was fabricated in Thailand. Phase 3 for the same was fabricated in Sapura. MMHE was floating budgetary ITB for this project. In the meantime, Sapura there is quiet for this project.........weird.My personal guess this project will fall on Sapura hand again, if follow the pass record......... |
|
|
Nov 28 2019, 06:18 PM
Return to original view | Post
#13
|
![]()
Newbie
40 posts Joined: Aug 2009 |
QUOTE(Stamp @ Nov 28 2019, 05:40 PM) MMHE is salivating over Limbayong’s multiple modules from the winning bidder (hot favourite is SIP). If MISC wins the job, MMHE also will be building the modules. And there is the upcoming CPP Jerun EPC Bid. Just received update from MMHE, they only gave a standard answer: Still under bidding, no news. For Jerun CPP............Bapa sure jaga anak baik2 . You know what i mean.... |
|
|
|
|
|
Nov 28 2019, 06:21 PM
Return to original view | Post
#14
|
![]()
Newbie
40 posts Joined: Aug 2009 |
|
|
|
Nov 28 2019, 06:52 PM
Return to original view | Post
#15
|
![]()
Newbie
40 posts Joined: Aug 2009 |
|
|
|
Dec 2 2019, 02:10 PM
Return to original view | Post
#16
|
![]()
Newbie
40 posts Joined: Aug 2009 |
Just do a fact check here. Heard Lekir Bulk Terminal phase 2 already called off, can verify here?
Thanks! |
|
|
Dec 16 2019, 10:27 AM
Return to original view | Post
#17
|
![]()
Newbie
40 posts Joined: Aug 2009 |
|
|
|
Dec 24 2019, 09:06 AM
Return to original view | Post
#18
|
![]()
Newbie
40 posts Joined: Aug 2009 |
|
|
|
Jan 20 2020, 12:46 PM
Return to original view | Post
#19
|
![]()
Newbie
40 posts Joined: Aug 2009 |
QUOTE(AyamTNB @ Dec 26 2019, 08:26 AM) Heee please keep us posted Jerun CPP: Very high chance goes to Sapura Energy, reason you know i know. They will work with engineer company either Petrofac RNZ or RWP?? FEED study already done and probably Mid of 2020 for EPCC bidding.Btw let's share your input on below projects: Jerun CPP: Finalize in 2020/21?... MMHE/SapuraOMV? Ngenggggggg Rosmary: Sunyi... any update so far? Worley Feed.. delay meh? Langsat Terminal Phase 3: Think Dialog is doing it next year? Lawas Oil Refinery: Sinopec Design... Beli? Heard anything? Hess Phase 4: I think sapura will continue this one.. phase 3 they got... what do you guys think? Sarawak Petchem: You guys know oledi... Samsung.. now floating ITB Bintulu Methanol: SKG supply gas... Uchem EPCC... correct? Shell Crux : Looks like Sapura will get... already talking bout PA Aramco : Also looks like Sapura... but dunno how confirm the rumors are BAGSF 2 : Help me on this... PD&T is doing it now... Sipitang Oil Storage : long way to go... but Petroventure??? Diwangsa & Rhuara : Any update on this? Terengganu & Pahang project Langsat Terminal 3: Coming soon, probably kick off Q1?? Procurement activities is started, owner is looking subcon. Shell Crux: Sapura high chance, but don't know when the LOA is coming BAGSF2: Toyo consortium high chance to get. Heard the result come out Q1 2020 BTW, for Bayan MOPU, any details can share? Like project consultant, bidders.....etc |
|
|
Feb 19 2020, 06:05 PM
Return to original view | Post
#20
|
![]()
Newbie
40 posts Joined: Aug 2009 |
QUOTE(AyamTNB @ Feb 19 2020, 10:58 AM) Seriously?? They really go with 0% or negative margin as usual though... then press the vendor.. No wonder i glance through the BQ from MMHE, rasa pelik-pelik punye......As I've been thinking, they know perception weighs more on Sapura so they are doing the strange thing. Vendors should help quote them also! |
|
Topic ClosedOptions
|