 Home Defect Rectification Checklist, After vacant posession! Update With Pics

views
     
sheiberlee
post Apr 9 2016, 10:35 AM

Getting Started
**
Junior Member
155 posts

Joined: Feb 2008
QUOTE(mister_giam @ Apr 7 2016, 01:21 PM)
can you please share what are the price range (im not asking for quotation) for the service? depends on psf or how's that works? thank you smile.gif
*
depends on the psf bro. RM1 psf for the inspection
sheiberlee
post Apr 9 2016, 10:45 AM

Getting Started
**
Junior Member
155 posts

Joined: Feb 2008
QUOTE(noiseemunkee @ Apr 7 2016, 02:22 PM)
hi guys. in HDA and in SNP there is clause describing the completion of common facilities stating that the commong facilities of the development shall be completed by Vendor within 36 calendar months from the date of agreeement (SNP). The vendor architect shall certify the date of completion of common facilities.

If the vendor fails to complete the common facilities in time, vendor shall pay immediatelyto purchaser liquidated damages to be calculated from the day of the rate of 10% per annum of the last 20% of the purchase price.

Is the Completion of Common facilities tied to the VP? if the VP obtained late, does this mean purchaser have the right to ask for the LAD including common facilities with the same duration?
*
i think the developer calculation for your LAD are including the common area.

 

Change to: