Home Defect Rectification Checklist, After vacant posession! Update With Pics
|
mustang
|
Jul 5 2014, 11:18 AM
|
|
Hi guys I will be getting my keys soon and I would like to check with you all on my understanding on the DLP clause in the SnP as in the attachment My situation: All outstanding payments has been paid (Full bank loan has been released to developer) Per my understanding, on the 2nd clause, after 30 days the defect list has been submitted to the developer / site project lead and if it is still not fixed within 30 days, I cannot claim from the developer if I were to fix the defects myself as there is no outstanding payments. Not sure if I understand the term correctly. Thanks
|
|
|
|
|
|
mustang
|
Jun 23 2015, 09:21 PM
|
|
QUOTE(honkkydorry @ Jun 22 2015, 11:15 PM) During joint inspection with developer upon VP must we submit the defect report on that day itself or can I tell the technician I will submit after a much thorough inspection by me. You can submit at a later date. Just make sure it is within the DLP period as stated in your agreement.
|
|
|
|
|
|
mustang
|
Jun 28 2015, 01:54 PM
|
|
QUOTE(honkkydorry @ Jun 23 2015, 10:46 PM) Thanks. Actually why need to have joint inspection... In my personal opinion, the joint inspection is to enable the owners to have a view on the standard fittings in the house. They wont be able to have a thorough session with you to find out potential defects which is why you will need to do it and submit the list to them
|
|
|
|
|