Home Defect Rectification Checklist, After vacant posession! Update With Pics
|
honkkydorry
|
Jun 22 2015, 11:15 PM
|
|
During joint inspection with developer upon VP must we submit the defect report on that day itself or can I tell the technician I will submit after a much thorough inspection by me.
|
|
|
|
|
|
honkkydorry
|
Jun 23 2015, 10:46 PM
|
|
QUOTE(mustang @ Jun 23 2015, 09:21 PM) You can submit at a later date. Just make sure it is within the DLP period as stated in your agreement. Thanks. Actually why need to have joint inspection...
|
|
|
|
|
|
honkkydorry
|
Aug 12 2015, 01:08 PM
|
|
Need some advice from fellow experienced forummers. I have submitted my defects list to developer and they have started doing the rectification works but there was no activity for the past one week. From the list I submitted, most of the minor defects have been rectified but the major ones (doors and ceilings) have not been recifitied. When I called, I was told I am in the queue list. I am into the 3rd week from the date I submitted the list.
If there is still no activity resuming by the end of the 4th week, can I still write to the developer and tell them I will get my contractor to rectify the rest of the defects and billed to the developer?
|
|
|
|
|