post Mar 24 2022, 06:47 PM

New Member
*
Newbie
16 posts

Joined: Nov 2011
QUOTE(123wmike @ Mar 24 2022, 06:18 PM)
Hi wanna ask a cluster house under MBSA, wanna extend side for wet kitchen and first floor. Side land is 10feet. Wanna extend till about 9 feet same with the house behind of mine.

Was told by some reno cannot get CCC coz MBSA will never approve but you still can do it coz everyone did it, but most of  them extend only single floor.

Some reno said can get CCC. Any idea on which statement is true?

BTW how important is CCC for the extension? Easy to sell in future?
*
user posted image
user posted image

this is the renovation guideline for cluster house under mbsa
mayonzz
post Jun 13 2022, 09:38 AM

New Member
*
Newbie
16 posts

Joined: Nov 2011
QUOTE(dwh90 @ Jun 13 2022, 02:40 AM)
Hi seeking some advice here.

I just engaged a contractor and architect firm with 20 yesrs + establishment( both my dad's acquaintance ) for a double storey with major renovation in PJ. Currently deposit paid while  the architect and engineer fees cost me 15k till get a CCC while initially I insisted it badly as I wanted extension of the house to be recognised and things were agreed no problem and all.

So now thing changed, even i obey with the setback requirement on the extension, now being told that roofing structure change need KM approval and might not approve while the small things like gate pillar height etc to be comply if not will not get CCC and adviced me to proceed with approved plan and permit but build not following the plan n will not having a CCC. So I felt damn cheated because I'm paying an expensive architectural profession but providing such solution to me and if you are experience enough to know anyhow not approve then dont say no problem at the beginning right?  which I could anyhow just pay someone to submit standard plan n get reno permit and I do whatever I want.

So does anyone could be familiar with the procedure or able to provide a piece of advice please? 🙏

Professional here could PM me as well to explore
*
house renovation usually doesn't require submitting KM for approval unless u are converting it to another usage other than as a house like those bridal & bicycle shops in ss2.

and yes.. you have to build it according to the approved plan. eventho the architect who is the person to issue the CCC, but masjlis has the right to issue an order to stop the issuance of it if they find out to have breached the approved plan

mayonzz
post Jun 13 2022, 08:50 PM

New Member
*
Newbie
16 posts

Joined: Nov 2011
QUOTE(donmaikeru @ Jun 13 2022, 07:37 PM)
For MPSJ, do I need a permit to do an awning?
*
yes... awning for carporch area only under 'permit kerja-kerja kecil / pelan setara'

This post has been edited by mayonzz: Jun 13 2022, 08:50 PM
mayonzz
post Nov 9 2022, 06:45 PM

New Member
*
Newbie
16 posts

Joined: Nov 2011
QUOTE(GravityFi3ld @ Nov 9 2022, 04:36 PM)
Property is terrace house under MBPJ jurisdiction, and have neighbors on both sides (left & right).

Aside from applying the MBPJ Permit, is it also compulsory to get a separate letter, for the left and right side neighbors to consent to the works?

If they (or either one of them) do not consent, how do we proceed?
*
So far, MBPJ doesn't require any consent letter from neighbours
mayonzz
post Dec 3 2022, 09:10 PM

New Member
*
Newbie
16 posts

Joined: Nov 2011
QUOTE(kuai_chai @ Dec 2 2022, 11:58 PM)
hi,
recently i bought a sub sale house in kl, dbkl area.
i plan to extend the house, car porch area.
contractors have been telling me to get approval from dbkl. some said that now can submit online. and there is some standard plans to follow.
may i know is that true that we can submit online?
what is the website?
where to get the standard plans?
what is the requirement?
*
yes... submit online under KLIS-DBKL (kuala lumpur integrated submission)
there is no standard plan under dbkl, everything needs to be submitted either by architect / registered draughtsman
unless u are doing minor works which categorised under 'Permit kerja kecil'


 

Change to:
| Lo-Fi Version