Last heard from their staff, expected completion date is around June2015.
Garden Plaza @ Cyberjaya [Owners' Thread], Lifestyle Suites & Shops
Garden Plaza @ Cyberjaya [Owners' Thread], Lifestyle Suites & Shops
|
|
Apr 7 2015, 12:46 PM
Return to original view | Post
#1
|
![]() ![]()
Junior Member
273 posts Joined: Feb 2007 |
Last heard from their staff, expected completion date is around June2015.
|
|
|
|
|
|
May 20 2015, 03:47 PM
Return to original view | Post
#2
|
![]() ![]()
Junior Member
273 posts Joined: Feb 2007 |
MahSing sent a letter many months ago, that the project was extended by 6 months. Expected delivery month is June-2015. Hope it will be done by then...
Anyone has any updated pictures of GP ? |
|
|
Sep 16 2015, 03:13 PM
Return to original view | Post
#3
|
![]() ![]()
Junior Member
273 posts Joined: Feb 2007 |
A bump. According to MS, currently waiting for CF....
|
|
|
Nov 30 2015, 03:13 PM
Return to original view | Post
#4
|
![]() ![]()
Junior Member
273 posts Joined: Feb 2007 |
|
|
|
Dec 4 2015, 02:43 PM
Return to original view | Post
#5
|
![]() ![]()
Junior Member
273 posts Joined: Feb 2007 |
QUOTE(yiisingchiu @ Dec 2 2015, 03:52 PM) I received mine at the end of March. It was around Rm 1270. I checked with TNB Website. It should be only Rm 500. I wrote in. In July they informed me that it should only be Rm 500 plus Rm 10 Stamp duty. Lesson learnt: Don't just pay what the developer demands even a reputable one like Mah Sing. Find out and write to them telling them that they are wrong. Could it be just pretending that they don't know the actual rate so that they can make make more money from poor consumers? I called mah sing previously and asked them about this too. They said any extra payment will be put in to your 'account'.Anyone doing LAD ? This post has been edited by jex-koi: Dec 4 2015, 02:44 PM |
|
|
Dec 4 2015, 03:09 PM
Return to original view | Post
#6
|
![]() ![]()
Junior Member
273 posts Joined: Feb 2007 |
I just spoke to MS Icon Property. Their contacts,
Nazira (MS Icon Property, ext 438) Jane (MahSing, ext 379) Here's the summary : 1) TNB/Water/Syabas bulk meter deposit. Total RM821.45 (as stated in my letter, so it may differ with yours) - Deposit will be held by Property-management, MS Icon Property - Once JMB is formed, it will be passed from MS Icon to JMB 2) Previously owner paid TNB deposit of >RM1xxx - Any extra from this amount can be offset with any outstanding payment (like the #1 above) - Call Jane to see what's your account balance |
|
|
|
|
|
Dec 22 2015, 09:35 PM
Return to original view | Post
#7
|
![]() ![]()
Junior Member
273 posts Joined: Feb 2007 |
|
|
|
Dec 22 2015, 09:37 PM
Return to original view | Post
#8
|
![]() ![]()
Junior Member
273 posts Joined: Feb 2007 |
QUOTE(BombBird @ Dec 21 2015, 09:33 PM) Key collection have to wait Long queue until early Jan. Mah Sing is understaff and does not plan to work on weekends It seems we don't need to apply. When I called MahSing, they told me that my LAD will be ready later. Just call them and see when is yours ready.LAD can only apply after VP collection? Or can start immediately? |
|
|
Jul 14 2017, 03:34 PM
Return to original view | Post
#9
|
![]() ![]()
Junior Member
273 posts Joined: Feb 2007 |
Does anyone know whether there is Unifi there ? I saw Time fiber there before.
Nvm, i just confirmed. There is no unifi available at the moment. This post has been edited by jex-koi: Jul 14 2017, 04:11 PM |
|
|
Sep 12 2017, 08:55 PM
Return to original view | Post
#10
|
![]() ![]()
Junior Member
273 posts Joined: Feb 2007 |
My toilet previously leaked from the top-floor bathroom. Developer did not rectify even after a few weeks of formal notification. They only fix it when I make noise in their office... Mah Sing did a rush and bad job.
Anyone else facing leaking issue in the toilet ? |