ulala2
post May 18 2016, 04:08 PM

Getting Started
**
Junior Member
245 posts

Joined: Jul 2007
QUOTE(chickenessence @ Apr 29 2016, 06:24 PM)
I am wondering what we can do if the developer delay or take no actions about the defects. Happened to my friend that just collect key which condo just got VP recently.
*
Please check your SPA, there is always a term that related to defects. In standard practice, upon received the defect list from you, developer have 45 days to rectify the defects. In the event the defects is not rectify after 45 days,

1) purchaser need to obtain a quotation from third party;
2) issue a letter to developer where your intended to rectify the defects yourself by enclose the quotation;
3) if no feedback from the developer with the specific period, you can proceed with the work and claim back from the developer.
ulala2
post Apr 25 2019, 09:15 AM

Getting Started
**
Junior Member
245 posts

Joined: Jul 2007
QUOTE(zhou.xingxing @ Apr 24 2019, 10:52 AM)
anyone experienced this during sub divide? got shown a letter that says the subdivision plan has been approved.. letter is dated aug 2018... called the surveyor why stil not settled and all he says is "now just wait for the land surveyor to call you to surrender and exchange title". as of april 2019, still not received any calls.
*
Please provide more details.
Landed, strata development, or subdivide land or ???
ulala2
post Apr 25 2019, 06:17 PM

Getting Started
**
Junior Member
245 posts

Joined: Jul 2007
QUOTE(zhou.xingxing @ Apr 25 2019, 09:18 AM)
subdivide land. it was a land shared between dad and uncles. so after dad passed away. need to subdivide one title to 3 titles. the surveyor already come our land to survey twice and the letter mentioned that the land subdivision plan has been approved. just wait for the call.
but this call, is like taking forever. as the letter mentioned is dated aug 2018. now alr apr 2019. feb time got call the surveyor doing the subdivision. he just keep says just wait for the damn call. frus mad.gif
*
if the plan is approved, normally PTG may take few months to issue the new title.
ulala2
post Jan 15 2020, 05:12 PM

Getting Started
**
Junior Member
245 posts

Joined: Jul 2007
QUOTE(iwubpreve @ Dec 3 2019, 09:32 PM)
what schedule u talking about? for buyer usually just pay when developer claim the money via stage completion
*
Schedule H for high rise building,

Schedule G for landed property
ulala2
post May 15 2020, 11:46 AM

Getting Started
**
Junior Member
245 posts

Joined: Jul 2007
QUOTE(Yoh @ May 14 2020, 04:22 PM)
how do i get old house floor plan? is it available in government office?
*
Go back to the developer or consultant team if possible. or if high rise, may be MO office.
ulala2
post Dec 28 2020, 11:56 AM

Getting Started
**
Junior Member
245 posts

Joined: Jul 2007
QUOTE(Cmyong88 @ Nov 19 2020, 09:42 AM)
What happens when a high rise project with multiple blocks failed to obtain strata title? What does that mean to developer, owner and potential buyer?
*
They may have many factors why they c't obtain the strata title.
Commond problem for old project before SMA 2013: -

1) Do not have SIFUC / Schedule of Parcel approval;
2) Delay in government agencies like COB, Surveyor Department, Land Department (very common)
3) Delay by their surveyor to carry out the final as-built measurement

Problem to owner may have some difficulties to borrow money, to sell the property and so on.
ulala2
post Jul 26 2021, 12:36 PM

Getting Started
**
Junior Member
245 posts

Joined: Jul 2007
QUOTE(faridfauzi @ Apr 13 2021, 02:26 PM)
Hello, my brother has purchased one townhouse at Bandar Seri Putra.

Currently the house has small flow to overall house (from tank). The bathroom is so small, the shower water still small (using water heater with DC pump).
When he complained to the developer, their said they have meet the minimum requirement.

Is there any legal document mentioned minimum flow requirement for house pipe and its criteria?
*
Potentially u may need to search from Uniform Building by Law (UBBL) or local authority design guidelines.
ulala2
post Sep 24 2021, 09:01 AM

Getting Started
**
Junior Member
245 posts

Joined: Jul 2007
QUOTE(drbone @ Sep 2 2021, 11:14 AM)
What's the best way to ensure a closed up maid room, with louvre door? Will the room still be stuffy?
Will installing a ceiling exhaust be of much help?
*
You may consider installing a standard exhaust fan as people install it in the kitchen.

 