 Ask me anything abt Construction Industry!, Q&A

views
     
Morningkaki P
post Jul 19 2020, 02:36 PM

New Member
*
Probation
1 posts

Joined: Jul 2020
Hi iwubpreve,

I bought an apartment in Apr 2016. According to the agreement, the parcel should be ready for handover within 30 months from the SPA date (7 Apr 2016). Meaning the due date is 7 Oct 2018. However, the progress of the project has been stagnant after they have done piling since year 2017. There is no further progress until now.

May i know is there anything that we, as a buyer, can do to push the developer?
Can we start claiming the LAD now before the parcel handover?

Appreciate your advise.

 