 PLAZA RAKYAT of Pudu / Bukit Bintang, The Arbitration Outcome and Future

views
     
TSbb68
post Dec 9 2014, 02:04 PM

Enthusiast
*****
Senior Member
718 posts

Joined: Oct 2013
Pledge to Plaza Rakyat buyers

http://www.thestar.com.my/News/Community/2...ests-will-be-l/

PURCHASERS of the abandoned Plaza Rakyat project in Jalan Pudu have been assured that their investments will be returned either in the form of new units or cash payments.

Federal Territories Minister Datuk Seri Tengku Adnan Tengku Mansor said the matter would be solved at the end of the month when the government awards the contract to develop the place to the new developers.

“We hope to solve it by the end of the month after we make the award.

“The new developer has been told it must uphold the interests of Kuala Lumpur City Hall (DBKL) and the buyers. We will make sure they do so.

“Apart from the need to revitalise the project, we have always been concerned about the rights of the buyers,” Tengku Adnan said.

“If the buyers want cash, the developer will make sure they get their money back, and if they want units in the new development, they will get that.

“Please have faith in the Government,” he stressed.

Last week, StarMetro reported that DBKL had taken vacant possession of the site.

Excited over the news, several buyers had called the newspaper saying they wanted the Government to ensure they received the units they purchased decades ago.

A total of 221 business lots were sold 20 years ago when the project was launched.

Today, there are about 200 buyers, many now in their twilight years, who had invested their life savings in the Plaza Rakyat project.

In 2011, about 20 buyers lodged police reports at the Tun H.S. Lee police station demanding compensation and refund of their downpayment for the abandoned project.

jasonpang
post Dec 9 2014, 04:41 PM

Getting Started
**
Junior Member
147 posts

Joined: Dec 2012
QUOTE(bb68 @ Dec 9 2014, 02:04 PM)
Pledge to Plaza Rakyat buyers

http://www.thestar.com.my/News/Community/2...ests-will-be-l/

PURCHASERS of the abandoned Plaza Rakyat project in Jalan Pudu have been assured that their investments will be returned either in the form of new units or cash payments.

Federal Territories Minister Datuk Seri Tengku Adnan Tengku Mansor said the matter would be solved at the end of the month when the government awards the contract to develop the place to the new developers.

“We hope to solve it by the end of the month after we make the award.

“The new developer has been told it must uphold the interests of Kuala Lumpur City Hall (DBKL) and the buyers. We will make sure they do so.

“Apart from the need to revitalise the project, we have always been concerned about the rights of the buyers,” Tengku Adnan said.

“If the buyers want cash, the developer will make sure they get their money back, and if they want units in the new development, they will get that.

“Please have faith in the Government,” he stressed.

Last week, StarMetro reported that DBKL had taken vacant possession of the site.

Excited over the news, several buyers had called the newspaper saying they wanted the Government to ensure they received the units they purchased decades ago.

A total of 221 business lots were sold 20 years ago when the project was launched.

Today, there are about 200 buyers, many now in their twilight years, who had invested their life savings in the Plaza Rakyat project.

In 2011, about 20 buyers lodged police reports at the Tun H.S. Lee police station demanding compensation and refund of their downpayment for the abandoned project.
*
<solve it by the end of the month after we make the award>

can solve at this month ?


TSbb68
post Dec 9 2014, 07:10 PM

Enthusiast
*****
Senior Member
718 posts

Joined: Oct 2013
QUOTE(jasonpang @ Dec 9 2014, 04:41 PM)
<solve it by the end of the month after we make the award>

can solve at this month ?
*
can gua...
TSbb68
post Dec 30 2014, 12:47 PM

Enthusiast
*****
Senior Member
718 posts

Joined: Oct 2013
New hoarding in sight! Work to resume soon smile.gif


Attached thumbnail(s)
Attached Image
jinsailoo
post Dec 30 2014, 02:34 PM

Look at all my stars!!
*******
Senior Member
2,036 posts

Joined: May 2010


it is good that this project resume ASAP,

remember last time when star LRT just started already abandoned,

i pass by their every day when i went to school
TSbb68
post May 31 2015, 10:49 PM

Enthusiast
*****
Senior Member
718 posts

Joined: Oct 2013

Xyclop
post May 31 2015, 11:27 PM

Getting Started
**
Junior Member
59 posts

Joined: Mar 2014


bb68


nexona88
post May 31 2015, 11:33 PM

The Royal Club Member
*********
All Stars
48,585 posts

Joined: Sep 2014
From: REality
woah needed to pay today market price shakehead.gif buyers suffer again doh.gif
owj
post Jun 1 2015, 05:02 PM

Enthusiast
*****
Senior Member
875 posts

Joined: Apr 2006


Question is if most of the buyers are in their twilight years and they need to buy at the current market price, how are they going to apply loan, if needed?

puchongite
post Jun 1 2015, 05:09 PM

20k VIP Club
*********
All Stars
33,725 posts

Joined: May 2008
QUOTE(nexona88 @ May 31 2015, 11:33 PM)
woah needed to pay today market price  shakehead.gif  buyers suffer again  doh.gif
*
Sooooo ..... grossly unfair !!!
nexona88
post Jun 1 2015, 05:14 PM

The Royal Club Member
*********
All Stars
48,585 posts

Joined: Sep 2014
From: REality
QUOTE(puchongite @ Jun 1 2015, 05:09 PM)
Sooooo  .....  grossly unfair !!!
*
yes.. really unfair...

the project is like sooo long delay shakehead.gif
TSbb68
post Oct 28 2015, 04:01 PM

Enthusiast
*****
Senior Member
718 posts

Joined: Oct 2013
Draining the capital’s biggest fish pond

THE STAR . BY BAVANI M.

user posted image

AFTER 20 years in limbo, the billion ringgit uncompleted Plaza Rakyat project will finally be revived and former buyers of the units will be duly compensated.

Last year Kuala Lumpur City Hall (DBKL) took vacant possession of the abandoned project site after repaying an RM150mil loan taken by its earlier developer Plaza Rakyat Sdn Bhd (PRSB) from a consortium of banks.

After months of negotiations, DBKL will ink the deal to surrender the site over to new developer, Profit Consortium Sdn Bhd, on Friday

Profit Consortium is owned by Maxcorp Development Sdn Bhd, SW Land Sdn Bhd and Tan Sri Abdul Samad Alias.

Maxcorp is the private vehicle of Major (Rtd) Anuar Adam while SW Land is the developer of Sungai Wang Plaza.

The original plan for Plaza Rakyat comprised a mixed development with a multi-storey office tower, condominium, hotel and a seven-storey shopping centre.

user posted image
A tricky part in rehabilitating Plaza Rakyat is draining the stagnant water from the basement car park.


The RM1.4bil project was 30% completed about 15 years ago when PRSB ran into financial difficulties during the 1997/1998 Asian financial crisis, forcing it to abandon the project.

Then in 2010, the government terminated PRSB’s contract, 12 years after the project was left abandoned.

Subsequently, PRSB went into receivership and came under the administration of a consortium of lender banks.

New lease of life

It will take a few more months for the developer to start work to rehabilitate the project as a full structural report must be carried out on the site.

DBKL Mechanical & Engineering Department officer Abd Jamil Abd Rahman said it would take engineers several months to assess the corroding steel structures such as rebars and scaffolding left behind after the project was abandoned two decades ago, to determine if it could be retained or incorporated in the new development.

He added that the real challenge lay with the task of draining the water from the seven-storey basement which had since retained rainwater for so long.

user posted image
A full structural report will need to be carried out to find out if the old steel roads and scaffolding remnants from the dead project can be reused.



The basement, dubbed the ‘swimming pool’ by DBKL officers, was now home to snakes and fish such as tilapia and haruan, which was said to be the most challenging part of the rehabilitation process.

“When we took over the site last year, we had to use four different pumps to drain out the water, which was at the same level of Jalan Pudu and the LRT pole.

“The site is located in a valley, so when it rains, the water will flow right into the basement.

“It was at a dangerous level and we needed to drain it out fast,” he said.

It took three months to drain the water out of only three levels of the seven-storey basement, he said, adding that the work had started in June.

“After Friday, the site will be surrendered to the developers, and their engineers will have to drain out the water from the remaining four storeys. That is not going to be an easy thing to do,’’ he said.

“We are also concerned, because the LRT is running above, and each time the train passes, it will vibrate, so all these are factors that need to be looked into,’’ said Abd Jamil.

A source familiar to the project said the new developers would only be able to determine the full extent of the work needed to be carried out to revive the project after their experts move in and assess the site.

“A complete structural integrity survey have to be carried out first.

user posted image
An aerial view of the abandoned Plaza Rakyat project in Jalan Pudu.


“The concrete and steel reinforcement roads were left exposed to the elements for almost two decades, and as the original plan was for a 79-storey office tower, a 46-storey condominium, and a 24-storey hotel, the foundation had been piled deep into the ground,’’ he said.

“While we have ideas on plot ratio and density, one cannot fully plan anything at this stage until a survey is carried out.

“They are working on the estimates on what can be retained from the old project site or incorporated into the new design as well as sorting out some minor land matters,’’ added the source.

This post has been edited by bb68: Oct 28 2015, 04:35 PM
owj
post Oct 28 2015, 04:44 PM

Enthusiast
*****
Senior Member
875 posts

Joined: Apr 2006


Wow. Got 7 storey basement?
kochin
post Oct 28 2015, 04:51 PM

I just hope I do!
********
All Stars
10,319 posts

Joined: Dec 2009
From: Malaysia


from the last pic, check out the site progress for 118.
seems to be moving full steam ahead.
KaFai
post Oct 28 2015, 06:07 PM

Casual
***
Junior Member
459 posts

Joined: Mar 2010
Nice to finally hear some news about this project.
nexona88
post Oct 28 2015, 07:03 PM

The Royal Club Member
*********
All Stars
48,585 posts

Joined: Sep 2014
From: REality
finally something good is happening rclxms.gif
HELLO HELLO
post Oct 28 2015, 09:11 PM

Look at all my stars!!
*******
Senior Member
5,436 posts

Joined: Jan 2011
Just turn it to little tropical Jungle rainforest+ Eco fish pond Can function as retention pond in the city. Put more soil, plant more trees only. Let the wild bird come rest rest. Tourist can visit n relax. This is what we lack of in the heart of the city. Sure become another tourist hot spot.

This post has been edited by HELLO HELLO: Oct 28 2015, 09:16 PM
nexona88
post Oct 28 2015, 09:51 PM

The Royal Club Member
*********
All Stars
48,585 posts

Joined: Sep 2014
From: REality
QUOTE(HELLO HELLO @ Oct 28 2015, 09:11 PM)
Just turn it to little tropical Jungle rainforest+ Eco fish pond Can function as retention pond in the city. Put more soil, plant more trees only. Let the wild bird come rest rest. Tourist can visit n relax. This is what we lack of in the heart of the city. Sure become another tourist hot spot.
*
cannot make so much $$ compare with condo / mall / office sweat.gif
nivota
post Oct 28 2015, 10:51 PM

Getting Started
**
Junior Member
183 posts

Joined: Jun 2010

if after the land assessment shown that it no longer suitable for high rise construction, they should make it become like a plaza/setiawalk type and integrating with nature
nexona88
post Oct 28 2015, 11:03 PM

The Royal Club Member
*********
All Stars
48,585 posts

Joined: Sep 2014
From: REality
if land "not suitable" for high rise construction, they would "make it" suitable for high rise whistling.gif

prime land in KL wor drool.gif icon_question.gif

19 Pages « < 4 5 6 7 8 > » Top
 

Change to:
| Lo-Fi Version
0.1376sec    1.25    6 queries    GZIP Disabled
Time is now: 22nd December 2025 - 02:09 PM