QUOTE(Jagalat @ Jun 3 2015, 11:54 PM)
In case they say everything is running per schedule, then you can turn to third schedule (clause 4) of your spa. Then you have power to ask them "According to the schedule, development should have been completed some stages and 2013 year buyers should be paying progressive billing, but none so far...Why ah? "
If they still deny, pls show them some pictures (two weeks ago) in the forum.
In case you need last weekend pictures, l can post them tomorrow. All the best!
In fact I ask the SA this question during my purchase and the SA do agree the project is behind schedule.
She told me that project schedule is behind about 6 months and currently they are speeding up the progress.
Do any sifu here have any info if ekovest really speeding up the progress or is the same?
Then I ask her if the project is delay, what is the LAD? and she reply me is 10% per annum and is stated in the SPA.
That's why I need the sifus here to advise me is the SPA standard? if yes, then is ok, else I better call them to send me the SPA that I am going to sign tomorrow to pre-read carefully before signing because tomorrow I am signing using their solicitor Susanna Lim & Partners.
Btw, is there any clause in the SPA that I need to take note or any question I need to ask the lawyer tomorrow during my signing?