This project competitor is "NETIZEN" ... which is bdr tun hussin onn.

The pilling construction is critical slow ....

This post has been edited by deschan100: May 30 2015, 09:42 AM
deschan100
post Jun 4 2015, 05:21 PM

Getting Started
**
Junior Member
121 posts

Joined: Jun 2010
QUOTE(cteh2 @ Jun 4 2015, 07:40 AM)
In fact I ask the SA this question during my purchase and the SA do agree the project is behind schedule.
She told me that project schedule is behind about 6 months and currently they are speeding up the progress.
Do any sifu here have any info if ekovest really speeding up the progress or is the same?

Then I ask her if the project is delay, what is the LAD? and she reply me is 10% per annum and is stated in the SPA.

That's why I need the sifus here to advise me is the SPA standard? if yes, then is ok, else I better call them to send me the SPA that I am going to sign tomorrow to pre-read carefully before signing because tomorrow I am signing using their solicitor Susanna Lim & Partners.

Btw, is there any clause in the SPA that I need to take note or any question I need to ask the lawyer tomorrow during my signing?
*
i not sure this project completion period is 3 or 4 years.

You S&P date is start from tomorrow, counting from tomoro 3 or 4 years.

If u dapat claim the late interest, that mean this project is over delay.