QUOTE(boyan @ Dec 7 2013, 08:04 PM)
Apologies for the late reply. Here's the chronology.
[2012 August] Keys received.
[2012 September] Defect work by developer. At this point, looking back at even older pictures (yay for documentation!), it seems like there were tell-tale signs of watermarks, though nowhere near as bad as now! Note that at this point, the original paint has already been there for few months, and it wasn't as bad.
Observe how it was also happening at the lower part of the wall, across the living hall.

A close up to one of the problematic areas:

[2013 February] Vacant for a long long time due to end of year, CNY and just timing issues. Work was restarted and hacking done to install aircond piping. Cement work done to patch up the wall a few days after that, around end of February
[2013 March ] Paintmen came to skim coat the walls only, around the end of March.
[2013 June] Work was put on hold due to timing issues (need to install timber floor before actual paint job), and also another defect found at a different area of the house. By June 10, work was restarted, and this is when paint is applied. At this point I didn't notice any watermarks on the wall (but it was just skim coating).
Aircond men then came around June 15 to install aircond.
[2013 August] I started to notice the watermarks at the living hall. They're probably worse than the ones I complained about during the defect report, but they're not as bad now. From June onwards sometimes I would visit the house *once* a week, at times turning the aircond 1-3 hours.
[2013 September] Scraped the peeling paint and repainted the wall again. I stopped using living hall aircond from this point onwards.
[2013 November / December] Messed up as per the posted pictures!
My gut feeling is
- the water problem was always there, even during VP. That's why I had to file some defects.
- the hacking for aircond piping worsened it. The hacking probably took out the 'good layer' of the wall which was holding back water to some extent
- the cement job to cover back the piping was never as good as the original wall / 'good layer', hence we see the paint deteriorating even faster!
How do you suggest I fix it?
!st, The Cause and Effect.
1. Your house is lower than your neigbor by 1 foot.
To save money and effort (work) the one foot below your neigbor was not plaster or simply "cincai" plaster since it is underground. This makes easy for underground water to seep into your side.
Anyway, even with good plastering ground water has no where to go as the floor is tiled. Water if not flow down by gravity will go up by capillary action or evaporation and condensed at the top solid layer where there is no way out. The only way out is to your side of wall, the one foot side. But then you may ask what about houses with same level? While when it is same level the water will go up all along the joint wall but not in as big volume. Under normal circumstances the evaporation continue right up to the surface of the wall through the paint (which is breathable. Breathable means vapor can pass thru) with little condensation. Even when there is a lot initially, by the time handover key (vacant possession) most of it has dried up as painting are usually done last. But for your case because it is one foot below neighbor ground, you have not only evaporation but a lot of capillary action as well. Anyway, even if you do not do anything under normal circumstances it will eventually dried up and you will not have water mark in future, but that will take some 5 years on average. That's is provided it is not make worse by your chilled aircond pipe as you have not one cause but 2 causes as below (2).
2. As explained in my post earlier, the chilled or cold aircond drain pipe draw in or suck more water and water vapour to the pipe due to condensation gas to liquid and the vacuum effect, make worst the situation. As you also mentioned the barrier to water had been made worse by the hacking for the pipe. The back of the pipe against the wall is not re-filled compactly with concrete.
Now, here is my suggestions. Let me start with the step you should do.
Step 1. Re-route the piping. That will solve cause (2) above. See picture below.
This will allow the chilled water to flow the minute it drip right up to the outside of the house and the chilled water has no time to cold the pipe for any chance of water condensation to take place. Moreover the high dried wall has little or no water vapor in it. If condensation has to take place it has to be from your living hall air's water vapor. Your living hall air as you swtich on the aircond, its water vapor or humidity has been taken away by your aircond! That is why your aircond dripping cold water (if you understand how aircond works you would understand this).
Step 1-1. cut the existing pipe somewhere shown in the picture, if not remove all of it till the manufacturer's flexible aircond drain pipe (that come with the aircond is even better) if it is not Class 7 pvc pipe.
Step 1-2. Buy a long one inch
Class 7 pvc pipe as the drain pipe. Class 7 has the thickest wall of all available pvc pipe classes. The thick wall itself provides heat insulation. There is no need for extra pipe insulation. Save money and work digging a deep and wide channel into the wall. Trust me. Never buy any other class especially Class 0 which aircond people usually use to save some little money and easy to work with. Class 7 is expensive comparatively and more stiff (hard to bend and to insert or fit into hacked channel)
Step 1-3. Do not start hacking. Make bend to the pvc pipe first as show in the above picture. Use gas stove heating up the pvc pipe soften it and make the bend shape, the aircond guy should know how to do this. Make wide bend not sharp bend so as to have smoother flow of water.
Step 1-4 Then draw the outline on the wall to be hacked and hack you go and the pipe should be at least half inch
inside wall surface. One inch is ideal. One half inch is ok. Too deep means a lot of hacking. The wall is 6 inches wide. Old house use to have 2 bricks wide wall, nowadays one brick. That mean you owned only 3 inches to your side.inside wall surface. One inch is ideal. One half inch is ok. Too deep means a lot of hacking. The wall is 6 inches wide.
Careful with this while hacking
1. There are at least 2 set of wire running along the wall and there shouild be a column for every 10 feet of wall, measured from the front column so roughly you know where it is. You have 2 column in this case as mark in the picture. So, do not allow the worker to use circular saw to cut the wall and accidentally or purposely (since they know) cut the wires. As for column it is harder to hack as it is a reinforced concrete that is not bricks but stone concrete and rebars. The circular saw make cutting job easy but it will cut the wire and rebar no matter how careful they are.
2. When rebar of the column in the way anyhow you must not be convinced by them it is ok to cut. Becuase they don't owned the house but you do mean they dont care if it is weaken. Go hack deeper avoid the rebars, the pvc pipe can bend. Like I said, they use class 0 becusae they can bend easily. They have to use heat again to bend the class 7. The vertical rebars MUST not be cut, the horizontal rebar that tied the vertical rebars can compromise(cut) but if can avoid best don't cut it.
Step 2....to be continued....