EdwinLN
post Oct 3 2012, 04:58 PM

New Member
*
Newbie
2 posts

Joined: Jun 2012


QUOTE(Slappy @ Sep 27 2012, 01:02 PM)
A very bad developer to watch out for:

PLENTIFIELD SDN BHD - Developers of Melaka Business Centre in Ayer Keroh

My experience with them:
- Bought a property in Sabah from them in 2009, a commercial shoplot run by Best Western hotel.
- Supposed to complete in Aug 2010.
- In Aug 2010 they told us delayed until Feb 2011.
- In Feb 2011 they told us delayed again until August 2011
- In Aug 2011 they told us delayed again until Feb 2012
- Now its Sep 2012 and property is still not handed over to me

- They are supposed to pay late interest of 8% pa to me. They refuse to pay.
- They are supposed to reimburse my loan interest payment (something like DIBS) - they refuse to pay for 2012
- They continually lied to us saying its completing soon and then suddenly they give me a letter saying that their engineers said in Nov 2011 asked for construction extension due to 'lack of manpower' and 'bad weather'.
- They are using said engineer's letter to get out of paying us late interest.

Overall, dishonest, lack of integrity, poor project management, poor customer service, poor everything.

Do not buy from this developer!!

If anyone has any other bad developers to share, it would be much appreciated also. Although these clowns are not blacklisted, we nee to know about them to save us alot of heartache!!
*
Hmm are you refering to the project in Melaka ??? As i know it is not even complete yet so how come they owe you late interest???
are you refering to some other project?


EdwinLN
post Nov 21 2012, 10:37 AM

New Member
*
Newbie
2 posts

Joined: Jun 2012


QUOTE(Ataman @ Nov 16 2012, 02:11 PM)
thanks slappy to sharing this information abt Plentifield.
Unfortunately, im already booked a unit in Melaka Business Centre but still yet sign the snp.
thinking abt should i lose the booking fee or pay another 10k to 15k to sign the snp? any advice?
*
Hi Ataman,

I'm glad that Slappy had put up his experience with this developer,
at first i was confused as the project in melaka was still in progress so how come
Slappy is talking about late interest in my previous post.

After researching finally found out,
the project Slappy bought in Sabah is done by a company called Equity Leader S/B.
Which brings me & my friends to another queries,
Slappy bought in 2009, and the project suppose to ready at aug 2010.
Given all the delayed information, it did sound the developer is late but
doesn't want to compensate to Slappy as per his/her allegations.
Snp in commercial properties usually are 36months from date of signing
Snp. So if we do some easy mathematics, although developer delayed
in the project Slappy still doesn't qualify to claim any Late interest of 8% right?
So maybe the developer did pay out the late interest to other purchaser but not to Slappy
which cause him to be pissed and posting here ? tongue.gif (just my assumption)

DIBS i cant comment on it, however as investor based in Malaysia
DIBS is quite a new concept which is introduced in recent years.
However if the developer guaranteed DIBS then there should be a documents
or undertaking by developer. So Slappy can easily bring this matter legally and
most developer hate court case and settle it so i dont see any big problem there.
Unless the DIBS was guaranteed to him by sales agents who wanted to do the sales
and Slappy himself took it for granted without checking the documents properly.
Sadly this kind of things still happens among some irresponsible agents,
once i book a condo with DIBS but when i'm about to sign Snp i notice
nothing was written about it and everything the agent told me was a fraud
so i make a formal complaint to the developer and got extra 3% discount biggrin.gif

Ataman, as investor we are responsible in all the documents we signed. So
my advice is make sure whatever the agent promised to you is written down
in the booking form & signed. Then keep a copy of it as proof. Any dispute with
developer show them the form and then let the developer settle it with their agents.
Make sure everything is stated in black & white before signing the Snp as after signing
it is too late to request for anything.
This is the safest way on purchasing.

I'm looking into their current project, it was interesting. Even make a visit to their office
in Melaka last week during Deepavali holidays. Building already 6th floor on structure.
Will be great if you can PM me what they offer you so maybe i could ask for the same tongue.gif
as i'm looking into buying it. Despite what Slappy said i think this project is worth investing.
Cant judge a box of apple based on 1 rotten apple right?

Look forward to your reply ataman. biggrin.gif



 