Ultimate LRT extension construction update thread!, Ara Damansara, USJ, Puchong!
|
callas
|
Nov 28 2012, 08:11 PM
|
New Member
|
i am not confident the kj line extension can complete on time as their project progress slow especially in Subang Jaya area (station 5-7).See no viaduct so far.
|
|
|
|
|
|
callas
|
Mar 13 2014, 04:59 PM
|
New Member
|
QUOTE(lilzany @ Mar 13 2014, 04:35 PM) this is very sadding. the area has seen the construction barrier since april 2011 and until now the piers are not fully up yet. if the best estimate is another year to put the viaduct and 1.5 year for testing.. project completion is well into 2017... what the f*** is TRC doing. no capability but bid for the biggest job Sunway viaduct is almost 90% complete from USJ 6 all the way to Putra Heights shops... +1
|
|
|
|
|
|
callas
|
Aug 13 2014, 11:35 PM
|
New Member
|
Bina Puri progress fast,whereas TRC...sigh!
|
|
|
|
|