TNB Registration, juz move in to a new house
|
MC_Amig0
|
Nov 23 2011, 01:38 PM
|
|
go to kedai tenaga. and register there.
if u have the previous bill, check the the bill, which kedai tenaga that the bill originated. then go there to register. u can used the same address for registration.
Added on November 23, 2011, 1:40 pmhave u call 15454.?
This post has been edited by MC_Amig0: Nov 23 2011, 01:40 PM
|
|
|
|
|
|
MC_Amig0
|
Nov 23 2011, 02:56 PM
|
|
not sure bro if they open on saturday. the best way to call 15454. ask any shop open on saturday. Added on November 23, 2011, 2:58 pmQUOTE(Skydrop @ Nov 23 2011, 02:55 PM) Find out how much deposit you have to pay. if he memory serve right, for single phase meter RM250 kot. for three phase meter RM750 or RM1000. This post has been edited by MC_Amig0: Nov 23 2011, 02:58 PM
|
|
|
|
|
|
MC_Amig0
|
Nov 23 2011, 04:58 PM
|
|
No lah. wrong info.
Added on November 23, 2011, 5:18 pmNo, you cannot register electricity under your wife name but there is an exception,
what u can do is that, u can write a letter to Pengurus Kawasan TNB( your kawasan lah)
in the letter saying that you will "mengizinkan" (dunno what english work for that haha)... you wife to register the electricity under her name, and attach together the ICs both of you and the house S&P agreement.
deposit for single phase is RM250. and for three phase is RM500.
but u also will be charge on "terminal connection" for
a) single phase = under 3 batang tiang is free but for more than 3 batang tiang ( RM300 per tiang) b) three phase = for overhead is RM750 and underground cable RM1500.
sorry just now i gave wrong info, have to verify with my TNBD counterpart as i am TNBT staff. haha.
hope this helps.
This post has been edited by MC_Amig0: Nov 23 2011, 05:24 PM
|
|
|
|
|
|
MC_Amig0
|
Nov 24 2011, 08:20 AM
|
|
QUOTE(Skydrop @ Nov 23 2011, 08:52 PM) Different area different deposit amount? I just did mine recently and have to pay RM300 for single phase + RM3 processing charges. you did huh? i have no comment, as i said, i am not with TNB Distribution customer service,(the one supply the electricity for us all) , i am with TNB Transmission (the one with high voltage tower..etc.). what i did yesterday is asking my TNBD cuctomer service colleague. i am not sure if different area impose different ? the fee that i was mentioned yesterday is in kluang haha.. last time i work there bro....
|
|
|
|
|
|
MC_Amig0
|
Nov 24 2011, 11:05 AM
|
|
QUOTE(adrianjc @ Nov 24 2011, 09:05 AM) You don't have to go buy stamp hasil or anything. TNB will do the necessary at the TNB shop. Best is to go yourself, if in doubt just call TNB and they should be able to clarify for you. that is correct. and go together with your wife.
|
|
|
|
|
|
MC_Amig0
|
Nov 25 2011, 08:41 AM
|
|
ok guys, i will take the issue to the TNB management. however, for new supply u all can use this link to register.. TNB Electricity online applicationhope this helps....
|
|
|
|
|