QUOTE(fast_coder @ Oct 12 2011, 09:57 AM)
my contractor's quotation is as follows, not the cheapest though.
you could use as comparison.
- Hood point RM 90 / each
- Oven point (direct) RM 200 / each
- Stove point (direct) RM 200 / each
- Air-cond point RM 200 / each
- Down Light point RM 50 / each
- Wall Light point RM 80 / each
- Power point RM 90 / each
- Fan point with hook RM 80 / each
- Ceiling Light point RM 50 / each
the downlight point is it includ downlight installation??you could use as comparison.
- Hood point RM 90 / each
- Oven point (direct) RM 200 / each
- Stove point (direct) RM 200 / each
- Air-cond point RM 200 / each
- Down Light point RM 50 / each
- Wall Light point RM 80 / each
- Power point RM 90 / each
- Fan point with hook RM 80 / each
- Ceiling Light point RM 50 / each