delay is due to disagreement between contractor (superstructure) and developer. The supersub contractor signed on was supposed to start in April but have pulled out. Anyways they've signed on a new contractor so keep your hopes up guys. Progress will be slow from ground floor to 4th/5th floor but after that it will go smoothly all the way to the top.
joefacker
post May 17 2012, 06:19 PM

Getting Started
**
Junior Member
72 posts

Joined: Aug 2009
i think you guys will be pleased to hear that you'll be paying for a very well built condo. One of the reasons why progress is quite slow is also because the developer's engineers and consultants are very strict and conduct checks on the progress almost everyday. Especially on the foundation (piling and pilecap), the structure has to be done in proper as it is this structure that will be holding the whole building up.

After pilecap will come the first few floors which will progress slowly as well but when they reach the 4th to 5th floor, it's full speed all the way up.

i think you can only sue them if they abandon the job or did not complete it in time.
joefacker
post May 18 2012, 02:54 PM

Getting Started
**
Junior Member
72 posts

Joined: Aug 2009
QUOTE(kochin @ May 18 2012, 08:38 AM)
bro joe, are you from the consultant team or the developer team.
thank you very much for sharing such news with us.
keep everybody updated here.
cheers!
*
hi bro, i'm neither from consultant or developer team...

my company supplied the concrete for the pilecaps...whereby we are lobbying with the contractor to supply the concrete for the superstructure (all the way to the roof) as well. As a concrete manufacturer we've supplied to plenty of projects from houses/shoplots, bridges, malls, high rise, factories, and so on. But this developer is one of the toughest we've worked with due to their very stringent checks. This is good for all parties because buyers will get a very good finished product, developer's name will grow due to the quality of their works and suppliers like us will be able to further work together with the developer on their next project since they are already comfortable with us.

This post has been edited by joefacker: May 18 2012, 02:54 PM
joefacker
post May 19 2012, 03:41 PM

Getting Started
**
Junior Member
72 posts

Joined: Aug 2009
you're welcome guys

will update accordingly when needed...

 