 Amansiara @ Jalan Ipoh, Selayang v2, congrats to P2 , P3 owners VP !!!!!

views
     
limee
post Jul 21 2009, 03:32 PM

New Member
*
Junior Member
8 posts

Joined: Jul 2009
Hi, I'm ph 1 onwer and just joined this group.

I received vp together with architect cert yesterday. FYI, my S&P due on 12/07/2009 and the completion date stated in architect cert is on 17/07/2009.
Is the VP valid?
Should I submit the LAD claim now or wait for CF issue?
limee
post Jul 21 2009, 04:18 PM

New Member
*
Junior Member
8 posts

Joined: Jul 2009
QUOTE(aironiq @ Jul 21 2009, 10:31 AM)
Hi all...I just collect my VP letter at Pos Laju this morning. I think I'm the 2nd batch to receive it. Well, in the letter they asked me to pay outstanding RM 1098.47 including interest on late payment by the bank to them. Shouldn't the late interest payment suppose the paid by the bank? it's their fault what ...anyway it just RM 40.17.

I just want to ask your guys opinion especially alan on my situation, my snp was expired in APRIL 09 ..and just now I've received my VP. I should entitle for LAD claim rite from the expiry date till the date I receive VP?

Hope to get CF soon...

------------------------
Just call Wirama office, A lady pick and forgot to ask her name...she said I need to check with my bank whether they have release the full amount the Wirama before I make an appointment with them to collect key. As for LAD...I need to write a letter to them stating how much they owe me and bring the letter together upon collecting key. Is this a correct way ?  rclxub.gif
*
My case is same as u.

WSB charged me the late payment interest, but I found that the late payment made from end financier. Therefore, I faxed my statement to end financier and ask them to clarify.

Innocent cry.gif sad.gif
limee
post Jul 21 2009, 05:10 PM

New Member
*
Junior Member
8 posts

Joined: Jul 2009
QUOTE(yeh.babe @ Jul 21 2009, 04:50 PM)
1.have you called to architect firm to verify? or alternatively call to mps to verify on the borang E submission date. mps will give you the confirmation letter on the date of acceptance, vp date should base on this date.

2. if you have done no 1, then vp is valid. then your LAd should be 13/7 to 17/7= 5 days

3. you can calculate your LAD = selling price x 10% x 5/365, then write in to developer to claim and request them to contra your LAD with your misc. payment. after the contra, if your LAD enough to cover misc pyt, then you req for $, if not enough, then you top up la.

4. LAD should stop on the day of VP & not cf date. vp date meaning developer submitted borang E & authority accepted the borang E. According to regulations, after borang E submission, within 14 days cf will be issued.

cheers..........
biggrin.gif
*
Just called to architect firm and confirmed that the borang E has been submitted, so I can bring my letter LAD to developer office and ask them to contra the outstanding payment for me, rite?

My LAD is not enough to cover the amount of misc payment. Can I just pay the balance after deduct the LAD.

limee
post Jul 22 2009, 10:38 AM

New Member
*
Junior Member
8 posts

Joined: Jul 2009
I just called WSB and asked whether can I contra LAD to settle my partial misc payment, but the person who answer the call said the management would not accept the matter of contra for settle payment. She asked me to write in first and wait for the approval.

Is this the normal procedure to claim LAD?