Just called and ask..

Was told about RM400psf.. It was comparable cheap in this BBB mode, even the Sg besi project also seeling this price.. Think PJ should sell higher than that rite?

So what you guys think? Any opinions?
blueswift
post May 13 2012, 09:15 PM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


Hi.. I will be attend if that is held on weekend..

Anyway, I am new here.. Mine is block A but I will turn myself on for the coming meet up.. Felt disappointed on the developer progress..

Nice to meet all of you..
blueswift
post May 17 2012, 12:08 AM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


Today went to Taipan HQ.. Asking about the handover date for block D owners.. There is an officer there but dunno what's his name and he mentioned that the keys are all get ready.. He showed me the boxes of keys on the floor and I noticed that the boxes are labelled with different unit numbers..

I was thinking to take photo but is a little odd to do so hence I didn't took any to show u guys here.. Anyway, I think this incident was really Syabas delayed as I got no idea that why the developer wanna delay since they already done and preparing to handover to the owners..

Btw, hope block D owners can get the VP by this month and the progress for other blocks keep moving lo.. smile.gif
blueswift
post May 25 2012, 12:01 AM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


Dear all.. So far my cheques have no issue.. The only incident happen was on March that the account departments delay a month payment.. ( mine was monthly collection basis).. Frankly at that point of time, I did doubt about the financial status of Taipan but after analyzing the progress claimant they've made and the completion of the condo structural, I think they should still be financial strong..

Mine was fifth floor at block A and the progress claim till now was only 35% where actually the block A structural was almost completed.. Beside, they are almost can handover block D but still keep delaying which all of us not sure what are they thinking but the only thing I can see here is if they really lack of money, they will be the one who really urge to handover as the can easily claim another 5% from all the units which estimated more than 4mil..

By the way, we should really meetup by this Saturday and need the management to reply the Syabas or any other issue which leading the delay.. Is better that mr Lau will join us for the meetup..

Can someone here initiate the meetup and update us the firm time and we together meetup in the sales gallery.. Kindly assisit in this matter..

TQVM!!
blueswift
post Jun 4 2012, 07:38 PM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


Jus passed by there.. The club house progress really slow.. Right now think they concentrate more on blocks A and B... They r linking both blocks together rite now..

The temple is still there.. Think block C and swimming pool will seriously delay..

Btw, really hope they get the approval from Syabas n no more further delay to issue the vp for block D residences..

Cheers n good luck..
blueswift
post Jun 21 2012, 06:57 PM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


Dear frens... Jus went to the sales gallery.. A staff still give the same excuse that Syabas causing the delay... They said probably next month only can get the keys...

Same story since early January... Boring...
blueswift
post Aug 15 2012, 08:08 AM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


ya.. why rent to african?
in PJ area wanna get a local ppl are so easy...
hopefully this is the one and ONLy one...
blueswift
post Mar 22 2013, 11:37 PM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


Good news.. Block A, B and clubhouse to be completed by June.. According to Taipan's Andy, he promised that and he will look after the comments and complaints..

If everything well conducted, I believe the condo price will easily touched 500psf in the next 2 years..

Cheers..

blueswift
post Mar 26 2013, 12:34 AM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


QUOTE(samjoywa @ Mar 25 2013, 09:42 PM)
My s&p sign on mid jan 2010 and is blok b, still not yet ready. What should I do? Please advise... Can I claim from taipan?
*
Yes.. U can claim.. Many our neighbors from Block D claim theirs.. I think the procedures are not very hassle.. Please bear in mind to stand firm upon claiming else •they• will neglect or delay to pay..

Good luck!!
blueswift
post May 13 2013, 10:08 PM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


QUOTE(arthas_teo @ May 13 2013, 04:38 PM)
interest to rent a unit or room at park51, any owner wan let go?
*
I wanna rent out mine at block A..

Details:
1,143 with 4 bedrooms facing bungalows/future icon city..
Available on July/August'13

Partly furnished:
3 ACs
2 heaters
Sofa set
Dining table
Kitchen cabinets with cooking stove
Washing machine
Refrigerator
Fans and lighting in all rooms

Asking rm1,900

Pm if interested

Thanks..


blueswift
post Jul 28 2013, 08:52 AM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


Dear ALL, I've checked with the HQ last week regarding the A and B handover period.

Same story as per previous, 2 more months to wait..

However, they mentioned this time is quite firm which BOMBA inspection is conducting and shall be end by Aug, so they said September can get CF..

The worry issue is A and B management will remain as per bock D which currently they are so many complaints from the existing D's neighbors.. So after we move in there should be more funds to maintain our condo and hopefully current issue will be eliminated..
blueswift
post Nov 5 2013, 05:40 PM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


Ya.. For Block A and B owners are still pending for VP.. But Mayb you can check with agents for the Block D units.. Probably, there are still some units pending for sales..
blueswift
post Nov 7 2013, 10:39 PM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


Park 51 really so good demand?! I think the main issue is you will never get a new and large unit in this price at PJ area..

I think for those who had holding power, probably after the completion of all facilities then price shall further up another 10~15%..

Since there are good rental demand, I believed Park 51's price still way to go up..

Density wise, I dun think there will be anyone to complaint about high dense.. If Park 51 consider high dense, then 1120, palm springs, parklane etc is considered congested highly dense condos..

Just my 2 cents..
blueswift
post Nov 12 2013, 11:12 PM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


QUOTE(utopia86 @ Nov 12 2013, 03:31 PM)
I just bought 994sf unit for 3xxk few months back. Looks like I am earning now. Luckily i made up my mind quick if not this good deal will just slip away.
*
How much is 994 able to fetch in this market?
blueswift
post Nov 16 2013, 10:50 AM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


QUOTE(arthas_teo @ Nov 16 2013, 07:27 AM)
taipan is sxxx developer. 1 year already still dun wan release cf
*
Ya, I am waiting for CF too.. Keep delaying.. The only hope is we can VP by 2013..
blueswift
post Nov 16 2013, 10:55 AM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


QUOTE(SMELOANPS @ Nov 16 2013, 04:31 AM)
R u property agent at there?
I interest to buy.

budget 450k, 1000sq above, aiming 7floor above
*
Hi there, I think is unable to find >1000 sqft with budget of rm450k..

I belief block D is fully transacted which mean whoever wanna sell already sold dy..

Moreover block A and B is little exclusive as there are only 8 units per floor and heard that the finishing will be slightly better than D, therefore for a unit with that size but ard rm450k is really impossible..

Anyway, good luck to you.. Hope we can be the neighbor soon..
blueswift
post Nov 16 2013, 11:10 PM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


QUOTE(mag9 @ Nov 16 2013, 04:15 PM)
now agent ask for 520k for 1143sq with 1 cp, low floor some more, i think i hav to give up park51, no fate..
*
So high? Thought there are a number in iproperty leas than rm500k?! No more? Ridiculous..

So rm520l that the agent intro to u is which floor n facing where?
blueswift
post Nov 16 2013, 11:15 PM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


QUOTE(arthas_teo @ Nov 16 2013, 02:18 PM)
hope will be release soon. promise last month release, gonna december soon. you are subsale or 1st owner?
*
I am the first owner..

Called sales office and was informed they r preparing the 2nd letter as they said the vp is by this month..

I dunno how true izzit but let's hope it happen by end of the yr..
blueswift
post Nov 18 2013, 03:02 PM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


QUOTE(Pennbattle @ Nov 18 2013, 09:25 AM)
last time block d oso delay but thanks to some resident manage to seek help from yb lau....oso syabas problem....maybe block a n b can gather together and seek help from yb lau......
*
I just called to HQ and was confirmed by the staffs that the VP is ready by next 2 weeks..

Developer is preparing the necessary docs send to owners and we shall start receiving these letters/ notification soon..

blueswift
post Nov 25 2013, 09:34 PM

Getting Started
**
Junior Member
52 posts

Joined: Apr 2011


Developer called and informed that VP either by this or next week..

They said they are sending the letters to the owners by this week to notify the key collection date..

They've stopped my reimbursement of interest claim and was informed the amount will be calculate upon key collection as we might need to pay some kind of fees/charges during vp..

I think we should start to draft the lad charges as mine has been delayed almost 1 full calender year..