Renovations 3-phase wiring

views
     
sonypshomer
post Jan 15 2019, 07:45 AM

Regular
******
Senior Member
1,594 posts

Joined: Aug 2017
QUOTE(JustNobody @ Jan 14 2019, 08:34 PM)
How much for your cost for wiring into your house?
*
Wiring not yet do. The wet work still havent complete
IceBikers
post Jan 15 2019, 01:29 PM

Enthusiast
*****
Senior Member
960 posts

Joined: Jan 2003


just a question, must the internal (wiring from meter to DB and DB box re-wiring) work has to be started right after TNB done the external work(3 phase wiring pulled, change meter panel and meter) ?

Can it like once TNB done, then TNB connect back existing 1 phase internal wire, electricity resume as normal, until schedule another time with contractor to do internal work.
SUSslimey
post Jan 15 2019, 03:04 PM


*******
Senior Member
6,914 posts

Joined: Apr 2007
QUOTE(IceBikers @ Jan 15 2019, 01:29 PM)
just a question, must the internal (wiring from meter to DB and DB box re-wiring) work has to be started right after TNB done the external work(3 phase wiring pulled, change meter panel and meter) ?

Can it like once TNB done, then TNB connect back existing 1 phase internal wire, electricity resume as normal, until schedule another time with contractor to do internal work.
*
Errr.
The wiring from internal db to meter is not the responsibility of tnb.
They can come and do the external part without any problem.
If the contractor is licensed and accredited by tnb they might be able to open the wire clamps of the tnb meter to install two more wire from internal to meter to finish the 3 phase, then install new clamps with and report the number on the clamps to tnb. This you will have to make sure and ask tnb and the contractor properly or you might face problems in future....like tempering with meter.
IceBikers
post Jan 15 2019, 03:57 PM

Enthusiast
*****
Senior Member
960 posts

Joined: Jan 2003


QUOTE(slimey @ Jan 15 2019, 03:04 PM)
Errr.
The wiring from internal db to meter is not the responsibility of tnb. 
They can come and do the external part without any problem.
If the contractor is licensed and accredited by tnb they might be able to open the wire clamps of the tnb meter to install two more wire from internal to meter to finish the 3 phase, then install new clamps with and report the number on the clamps to tnb. This you will have to make sure and ask tnb and the contractor properly or you might face problems in future....like tempering with meter.
*
I got this
the wires from meter (1 live 1 neutral) to internal DB is concealed --> require own assign electrician contractor to lay new wire from meter to internal DB and do the balancing.

I have a house at hometown where I'm not always back. I am wondering, can I first apply arrange with TNB to do the external wiring first, including changing the panel n meter.
TNB pull 3 wires (red, blue, yellow and 1 black neutral) to the meter, but only use one phase first with existing internal wire. the other 2 remain hanging uninstall.

So I can arrange with own contractor to do the rest internal work (hack and lay new cable from meter to internal DB, on another schedule.
SUSslimey
post Jan 15 2019, 05:40 PM


*******
Senior Member
6,914 posts

Joined: Apr 2007
QUOTE(IceBikers @ Jan 15 2019, 03:57 PM)
I got this
the wires from meter (1 live 1 neutral) to internal DB is concealed -->  require own assign electrician contractor to lay new wire from meter to internal DB and do the balancing.

I have a house at hometown where I'm not always back. I am wondering, can I first apply arrange with TNB to do the external wiring first, including changing the panel n meter.
TNB pull 3 wires (red, blue, yellow and 1 black neutral) to the meter, but only use one phase first with existing internal wire. the other 2 remain hanging uninstall.

So I can arrange with own contractor to do the rest internal work (hack and lay new cable from meter to internal DB, on another schedule.
*
What I am saying is this:
The bottom part where the meter is attached to the electric cable has cover with anti temper wire clamps that has numbers attached to the wire clamps.

That’s the part you need to clarify with your contractor and tnb. As any difference or evidence of tempering can and will be used against you.
IceBikers
post Jan 16 2019, 10:39 AM

Enthusiast
*****
Senior Member
960 posts

Joined: Jan 2003


ok , got it, thanks
tunasandwich
post Apr 9 2019, 03:18 PM

Enthusiast
*****
Senior Member
974 posts

Joined: Sep 2005
QUOTE(sonypshomer @ Jan 14 2019, 10:18 AM)
TNB just did my 3 phase around RM2.5k

But i have to pay extra since i want my meter to be outside the gate and the cable pull directly from the post (not from neighbor)

With waterproof housing and installation around RM1K
*
bro, means in total 3.5K? What's included in the 3.5K ah?

Also which area are you at ah?
sonypshomer
post Apr 9 2019, 03:20 PM

Regular
******
Senior Member
1,594 posts

Joined: Aug 2017
QUOTE(tunasandwich @ Apr 9 2019, 03:18 PM)
bro, means in total 3.5K? What's included in the 3.5K ah?

Also which area are you at ah?
*
1. new cable from pole
2. Bracket
3. Waterproof housing
4. Meter

Location Penang

This post has been edited by sonypshomer: Apr 9 2019, 03:21 PM
tunasandwich
post Apr 9 2019, 04:44 PM

Enthusiast
*****
Senior Member
974 posts

Joined: Sep 2005
QUOTE(sonypshomer @ Apr 9 2019, 03:20 PM)
1. new cable from pole
2. Bracket
3. Waterproof housing
4. Meter

Location Penang
*
thanks for the prompt reply bro! this doesn't include from the meter at the gate into the db in the house is it?
sonypshomer
post Apr 10 2019, 12:43 PM

Regular
******
Senior Member
1,594 posts

Joined: Aug 2017
QUOTE(tunasandwich @ Apr 9 2019, 04:44 PM)
thanks for the prompt reply bro! this doesn't include from the meter at the gate into the db in the house is it?
*
Nope
littlewing
post May 15 2019, 03:35 PM

Getting Started
**
Junior Member
246 posts

Joined: Oct 2009


guys i have a burning question, if upgrade to 3 phase. how do u know if u will kena surcharge for not using enough electricity?
voonmingloo
post May 15 2019, 07:51 PM

Casual
***
Junior Member
454 posts

Joined: Feb 2013
QUOTE(littlewing @ May 15 2019, 03:35 PM)
guys i have a burning question, if upgrade to 3 phase. how do u know if u will kena surcharge for not using enough electricity?
*
No Surcharge at all.
littlewing
post May 16 2019, 11:20 AM

Getting Started
**
Junior Member
246 posts

Joined: Oct 2009


QUOTE(voonmingloo @ May 15 2019, 07:51 PM)
No Surcharge at all.
*
Noted thank you
PaterB
post Aug 5 2019, 04:02 PM

New Member
*
Junior Member
35 posts

Joined: Aug 2007


Hi I'm trying to upgrade my house to 3phase, however the pole is not in front of my house but opposite. So they are are suggesting me to add another pole infront of my house which I dislike.

I asked them for the price of laying the cable underneath the road. They quote me RM25k!
Does it cost this much?
zackzihau
post Aug 6 2019, 10:52 PM

New Member
*
Junior Member
46 posts

Joined: Nov 2012
QUOTE(PaterB @ Aug 5 2019, 04:02 PM)
Hi I'm trying to upgrade my house to 3phase, however the pole is not in front of my house but opposite. So they are are suggesting me to add another pole infront of my house which I dislike.

I asked them for the price of laying the cable underneath the road. They quote me RM25k!
Does it cost this much?
*
If the quotes and reply is from TNB , then it's the accurate price , if not, then try to take picture and go Tnb ask properly , where's your location actually
bobowyc
post Aug 29 2019, 01:05 PM

You are who you are.
******
Senior Member
1,921 posts

Joined: Apr 2013
From: Petaling Jaya


Sorry to hijack your thread. What are the steps to get the tnb contractors to install 3phase wiring from the pole to my clients house? Area is ttdi and the internal 3phase wiring is done previously by another contractor but my client didnt do it until I started work at their place and now they want 3phase wiring. And may I know roughly how much it will cost? Any number of tnb which I can call and ask? Thanks guys.
littlewing
post Aug 29 2019, 04:11 PM

Getting Started
**
Junior Member
246 posts

Joined: Oct 2009


QUOTE(bobowyc @ Aug 29 2019, 01:05 PM)
Sorry to hijack your thread. What are the steps to get the tnb contractors to install 3phase wiring from the pole to my clients house? Area is ttdi and the internal 3phase wiring is done previously by another contractor but my client didnt do it until I started work at their place and now they want 3phase wiring. And may I know roughly how much it will cost? Any number of tnb which I can call and ask? Thanks guys.
*
where is your meter box located now?

to apply for 3 phase - go to my tnb self service portal and register. apply from there to upgrade your power from single to 3 phase. submit docs via online process and select a tnb certified contractor. he will come and assess and do submission for you. pricing depends on tnb assessment.


bobowyc
post Aug 29 2019, 05:50 PM

You are who you are.
******
Senior Member
1,921 posts

Joined: Apr 2013
From: Petaling Jaya


QUOTE(littlewing @ Aug 29 2019, 04:11 PM)
where is your meter box located now?

to apply for 3 phase - go to my tnb self service portal and register. apply from there to upgrade your power from single to 3 phase. submit docs via online process and select a tnb certified contractor. he will come and assess and do submission for you. pricing depends on tnb assessment.
*
Currently repositioned to outside. But I made a mistake of not calling them first... because now may need to hack for their wiring to be installed. doh.gif lol. Ohh. Okay I check now and see ya. hehe Roughly how much would it cost?
littlewing
post Aug 29 2019, 11:27 PM

Getting Started
**
Junior Member
246 posts

Joined: Oct 2009


QUOTE(bobowyc @ Aug 29 2019, 05:50 PM)
Currently repositioned to outside. But I made a mistake of not calling them first... because now may need to hack for their wiring to be installed.  doh.gif lol. Ohh. Okay I check now and see ya. hehe Roughly how much would it cost?
*
Submission fee 600-1.5k (depending how much the runner wanna charge u) - suggest u call them up before choosing one

Tnb Contribution fee- 1.7k (typically, unless special case)

Deposit top up abt - 200
bobowyc
post Aug 30 2019, 09:25 AM

You are who you are.
******
Senior Member
1,921 posts

Joined: Apr 2013
From: Petaling Jaya


QUOTE(littlewing @ Aug 29 2019, 11:27 PM)
Submission fee 600-1.5k (depending how much the runner wanna charge u) - suggest u call them up before choosing one 

Tnb Contribution fee- 1.7k (typically, unless special case)

Deposit top up abt - 200
*
SUbmission fee if i do through website is direct with tnb right?

57 Pages « < 49 50 51 52 53 > » Top
 