PETALING JAYA: Those travelling for work from Klang to Kuala Lumpur will have little to cheer, as the long‑anticipated Shah Alam LRT line (formerly LRT3) is now projected to be delayed to at least the second quarter of 2026.

According to industry sources, the primary cause of the delay lies in the final and most demanding stage of the project – system testing and commissioning

The line is currently undergoing a mandatory “fault-free run” as prescribed by the Land Public Transport Act 2010.

During this phase, the 22 trainsets, along with their wayside and supporting systems, must demonstrate the ability to integrate and operate continuously and reliably, as expected of a top-tier driverless train system using the Grade of Automation 4 (GoA 4) standard

Under this testing regime, the rolling stock, signalling, communications and electrification systems must all perform seamlessly together, not just in isolation, before the regulator, the Land Public Transport Agency (Apad), can certify the system as safe and fit for service.

Insiders say the trainsets have struggled to achieve and sustain the designated operating speed of 80-90kph, something which cannot be dismissed as a “minor issue”.

Full article https://www.thestar.com.my/news/nation/2025...ts-another-snag


fongsk
post Dec 8 2025, 10:28 AM

New Member
*
Junior Member
34 posts

Joined: Apr 2007
Stupid WKS. Anything under him surely delayed or problem one! I wonder how much he songlap!!!! 😡😡😡😡😡

Ehhh, transport minister is not him edi a? Then who? 😎

This post has been edited by fongsk: Dec 8 2025, 10:29 AM
Clueless07
post Dec 8 2025, 10:30 AM

Regular
******
Senior Member
1,372 posts

Joined: Oct 2012
Damn! last time say end Sept...
then project end Dec. Isnt 2 weeks ago already report as 31st Dec \


KNS- another 6 month delay. Really poor project management.
kcchong2000
post Dec 8 2025, 10:30 AM

Getting Started
**
Junior Member
189 posts

Joined: Jan 2009
Loke 7 said 31 December turn out is 31 dec 2026.
Lucas0323
post Dec 8 2025, 10:30 AM

Enthusiast
*****
Junior Member
808 posts

Joined: Aug 2011


Delay kan budaya kito. Why surprise pikachu face?
MR_alien
post Dec 8 2025, 10:31 AM

Mr.Alien on the loss
*******
Senior Member
3,582 posts

Joined: Oct 2007
From: everywhere in sabah



this is insane

31st december become second quarter of 2026?
mick84
post Dec 8 2025, 10:32 AM

Getting Started
**
Junior Member
96 posts

Joined: Feb 2021
Penalty the contractor je la...
prophetjul
post Dec 8 2025, 10:32 AM

10k Club
********
All Stars
12,287 posts

Joined: Oct 2010

Meanwhile in other small cities, without Monorail, LRT, MRT, etc

user posted image


TSPeopleOfPerlis
post Dec 8 2025, 10:32 AM

New Member
*
Junior Member
39 posts

Joined: Aug 2021
QUOTE(MR_alien @ Dec 8 2025, 10:31 AM)
this is insane

31st december become second quarter of 2026?
*
Second quarter 2026 become …
fongsk
post Dec 8 2025, 10:33 AM

New Member
*
Junior Member
34 posts

Joined: Apr 2007
QUOTE(Clueless07 @ Dec 8 2025, 10:30 AM)
Damn! last time say end Sept...
then project end Dec. Isnt 2 weeks ago already report as 31st Dec \
KNS- another 6 month delay. Really poor project management.
*
IN 4 JKOM asked if you take LRT or not? If no take, don kepoh! ☺️
fongsk
post Dec 8 2025, 10:33 AM

New Member
*
Junior Member
34 posts

Joined: Apr 2007
QUOTE(PeopleOfPerlis @ Dec 8 2025, 10:32 AM)
Second quarter 2026 become …
*
Y-suku Yamaha
teehk_tee
post Dec 8 2025, 10:33 AM

ไม่เป็นไร
*******
Senior Member
5,363 posts

Joined: Apr 2005
From: กรุงเทพมหานคร BKK

Loke serious gagal in project management n timeline delivery here.
Jenn77
post Dec 8 2025, 10:33 AM

Look Ma' Im Flyin! Gee~
*******
Senior Member
3,121 posts

Joined: Jan 2003
From: SA.KD.SA.KD


dafak.. mesti case x bayar sub-con la.
Matchy
post Dec 8 2025, 10:35 AM

Regular
******
Senior Member
1,330 posts

Joined: Jun 2019


LRT3 line set for Dec 31 launch pending final safety tests, says transport minister

https://www.malaymail.com/news/malaysia/202...minister/198749


above is Nov 17... just 3 weeks ago!
JustForCheonging
post Dec 8 2025, 10:36 AM

Getting Started
**
Junior Member
215 posts

Joined: May 2013


Lagi manatu MRT3? Senyap2 takda bunyi geh

This post has been edited by JustForCheonging: Dec 8 2025, 10:36 AM
MR_alien
post Dec 8 2025, 10:38 AM

Mr.Alien on the loss
*******
Senior Member
3,582 posts

Joined: Oct 2007
From: everywhere in sabah



QUOTE(teehk_tee @ Dec 8 2025, 10:33 AM)
Loke serious gagal in project management n timeline delivery here.
*
blame the contractor, not loke
i wonder what they found that can delay from 31st dec to second quarter? doh.gif
Clueless07
post Dec 8 2025, 10:42 AM

Regular
******
Senior Member
1,372 posts

Joined: Oct 2012
QUOTE(fongsk @ Dec 8 2025, 10:33 AM)
IN 4 JKOM asked if you take LRT or not?  If no take, don kepoh!  ☺️
*
i wanna take the free ride, the trial ride for 1st month. tongue.gif

as heard- there has been a lot of testing on going daily ( a college stay at condo right next to the track)
fongsk
post Dec 8 2025, 10:43 AM

New Member
*
Junior Member
34 posts

Joined: Apr 2007
QUOTE(Clueless07 @ Dec 8 2025, 10:42 AM)
i wanna take the free ride, the trial ride for 1st month. tongue.gif

as heard- there has been a lot of testing on going daily ( a college stay at condo right next to the track)
*
Ha Tudia… Walaun Cari pasal nak hentam kerajaan ! 😡😡😡😡😡😡😡😡😡
fongsk
post Dec 8 2025, 10:44 AM

New Member
*
Junior Member
34 posts

Joined: Apr 2007
QUOTE(MR_alien @ Dec 8 2025, 10:38 AM)
blame the contractor, not loke
i wonder what they found that can delay from 31st dec to second quarter? doh.gif
*
All DAP MPs telur? Have to handle delicately not to break them…
fongsk
post Dec 8 2025, 10:46 AM

New Member
*
Junior Member
34 posts

Joined: Apr 2007
QUOTE(Matchy @ Dec 8 2025, 10:35 AM)
LRT3 line set for Dec 31 launch pending final safety tests, says transport minister

https://www.malaymail.com/news/malaysia/202...minister/198749
above is Nov 17... just 3 weeks ago!
*
He probably learnt his lessons from KLIA aerotrain. He approved, showed off in X, thumbs up on aero train and boom! Problems starts. So now, thumbs down first before thumbs up…
ultramaman
post Dec 8 2025, 11:30 AM

Getting Started
**
Junior Member
168 posts

Joined: Jan 2010
From: 8.8.4.4



QUOTE(Clueless07 @ Dec 8 2025, 10:30 AM)
Damn! last time say end Sept...
then project end Dec. Isnt 2 weeks ago already report as 31st Dec \
KNS- another 6 month delay. Really poor project management.
*
not really poor project management can be entirely to be blamed.

i would assume, [educated guess]

project lama. project was delayed due to stop work order when change of gov . and the cost of the project came into question. so new gov available to reduce the cost, (but manage to reduce the cost by reducing number of stations) .
anyhow, issue is, some of the equipment or sensors most probably was purchased at the begining of the project. so now, they want to do commissioning but its a rojak of equipment and sensors , some new , some old . on top of that. someone had made announcement publicly that system will be ready <insert date> .

date announced without consideration worst case scenario timeline.

how ?

Jasonist
post Dec 8 2025, 11:46 AM

Oldfag
******
Senior Member
1,176 posts

Joined: May 2006
From: Memesia



anthony loke sila resign la... everything also delay or rosak
PathofLife
post Dec 8 2025, 11:52 AM

Getting Started
**
Junior Member
70 posts

Joined: Jun 2018
Literally Delay No More...owai
hirano
post Dec 8 2025, 12:15 PM

凸(`△´#)
*******
Senior Member
3,336 posts

Joined: Nov 2007
From: Pluto


/ktard here all bising, but i bet don't even use LRT/MRT daily
OPT
post Dec 8 2025, 12:31 PM

Wee wang wang
*******
Senior Member
2,065 posts

Joined: Feb 2011
Siapa cakap hari itu Menteri KPI cantik cantik
zeroty
post Dec 8 2025, 12:36 PM

Getting Started
**
Junior Member
95 posts

Joined: May 2007


Who awarded the contract to which contractor?
PathofLife
post Dec 8 2025, 12:37 PM

Getting Started
**
Junior Member
70 posts

Joined: Jun 2018
Rindu, zaman Anthony Loke go ride LRT spot check...owai
ZeroSOFInfinity
post Dec 8 2025, 12:37 PM

Look at all my stars!!
*******
Senior Member
3,703 posts

Joined: Oct 2005


QUOTE(MR_alien @ Dec 8 2025, 10:31 AM)
this is insane

31st december become second quarter of 2026?
*
It didn't say "end or beginning" of 2nd quarter 2026. Means can start as early as April, or latest by June (provided no more delays).

Suspect they want to ensure no hiccups like the Aerotrain issue, and that the "best' time to do is after the CNY-Raya holidays
danielmckey
post Dec 8 2025, 12:40 PM

Regular
******
Senior Member
1,053 posts

Joined: Jan 2008

Later postponed until end of 2026. Better just tell next year no need to give date. Trolling people is not a good sign.
SUSdattebayo
post Dec 8 2025, 12:55 PM

Look at all my stars!!
*******
Senior Member
5,366 posts

Joined: Aug 2005


You want to wear seluar pendek or not
You want to buy MKT or not
You want to mabuk2 or not

If anyone of the above is "yes"

You have no choice but to keep PH

#donemacaiplotek
MR_alien
post Dec 8 2025, 12:56 PM

Mr.Alien on the loss
*******
Senior Member
3,582 posts

Joined: Oct 2007
From: everywhere in sabah



QUOTE(ZeroSOFInfinity @ Dec 8 2025, 12:37 PM)
It didn't say "end or beginning" of 2nd quarter 2026. Means can start as early as April, or latest by June (provided no more delays).

Suspect they want to ensure no hiccups like the Aerotrain issue, and that the "best' time to do is after the CNY-Raya holidays
*
doesn't matter

if the news say delay by a few days or weeks, people maybe aren't so angry about it
but to directly say 2nd quarter is insane...like WTF they found out that can delay by that long rclxub.gif
Jigoku
post Dec 8 2025, 01:00 PM

Getting Started
**
Junior Member
289 posts

Joined: Jan 2010

QUOTE(MR_alien @ Dec 8 2025, 12:56 PM)
doesn't matter

if the news say delay by a few days or weeks, people maybe aren't so angry about it
but to directly say 2nd quarter is insane...like WTF they found out that can delay by that long rclxub.gif
*
.whatever they found out, action will take against contractors or not

If not then as always get away and songlap je la
Iceman74
post Dec 8 2025, 01:01 PM

Regular
******
Senior Member
1,407 posts

Joined: May 2010


QUOTE(MR_alien @ Dec 8 2025, 12:56 PM)
doesn't matter

if the news say delay by a few days or weeks, people maybe aren't so angry about it
but to directly say 2nd quarter is insane...like WTF they found out that can delay by that long rclxub.gif
*
Must be serious problem lor.
Need order special replacement plus shipping by sea and installation. That already 3 mths window period. After that, do testing again. Around there lor time frame
sankai80
post Dec 8 2025, 01:03 PM

freakish chicken
*******
Senior Member
2,019 posts

Joined: Jan 2003
From: Pumpkinland


QUOTE(Iceman74 @ Dec 8 2025, 01:01 PM)
Must be serious problem lor.
Need order special replacement plus shipping by sea and installation. That already 3 mths window period. After that, do testing again. Around there lor time frame
*
It’s better to solve the on hands problems first before launch, better than launch first fix later attitude. Of course I’m not discounting the seeking accountability part for the delay.
danielcmugen
post Dec 8 2025, 01:07 PM

Look at all my stars!!
*******
Senior Member
5,538 posts

Joined: Apr 2011



QUOTE(MR_alien @ Dec 8 2025, 12:56 PM)
doesn't matter

if the news say delay by a few days or weeks, people maybe aren't so angry about it
but to directly say 2nd quarter is insane...like WTF they found out that can delay by that long rclxub.gif
*
Better announce a more conservative timeline than over-promising
lorrydriverrocks
post Dec 8 2025, 01:11 PM

Getting Started
**
Junior Member
268 posts

Joined: May 2014
QUOTE(Clueless07 @ Dec 8 2025, 10:30 AM)
Damn! last time say end Sept...
then project end Dec. Isnt 2 weeks ago already report as 31st Dec \
KNS- another 6 month delay. Really poor project management.
*
QUOTE(MR_alien @ Dec 8 2025, 10:31 AM)
this is insane

31st december become second quarter of 2026?
*
U all didn't read the fine print ka ?

Keyword is LRT3 operations delayed to Dec 31 or later, there was no commitment to be ready exactly on Dec 31

https://theedgemalaysia.com/node/780900
ameliorate
post Dec 8 2025, 01:15 PM

Casual
***
Junior Member
370 posts

Joined: Jul 2010


Everything all finished la. Just cannot pass final inspection. Wtf punya contractor, must be cut cost here and there, use cikai parts etc.

Done protect my beloved Tony.

MegaCanonF
post Dec 8 2025, 01:16 PM

Enthusiast
*****
Junior Member
880 posts

Joined: Jan 2018
Misti sarahan LGE DAP
tomato people
post Dec 8 2025, 01:16 PM

Tomato fan
******
Senior Member
1,735 posts

Joined: Jul 2016
From: tomato land


Mrt in melaka pleaseee
DogeGamingPRO
post Dec 8 2025, 01:18 PM

Getting Started
**
Junior Member
170 posts

Joined: Mar 2014



Inb4 sarahan CCP trains
blanket84
post Dec 8 2025, 01:23 PM

Regular
******
Senior Member
1,521 posts

Joined: May 2008
QUOTE(MegaCanonF @ Dec 8 2025, 01:16 PM)
Misti sarahan LGE DAP
*
It is sarahan LGE. Mau cut cost here and there, end up everything delayed.
Imp Bron
post Dec 8 2025, 01:27 PM

Getting Started
**
Junior Member
143 posts

Joined: Aug 2014
QUOTE(Matchy @ Dec 8 2025, 10:35 AM)
LRT3 line set for Dec 31 launch pending final safety tests, says transport minister

https://www.malaymail.com/news/malaysia/202...minister/198749
above is Nov 17... just 3 weeks ago!
*
I think contractor already told next year
Higher up die2 push end of this year to push good KPI

Contractor ask they can but anything happen you tanggungjawab because you sign early release.

Client don't want to sign than this happen
anip94
post Dec 8 2025, 01:44 PM

Getting Started
**
Junior Member
101 posts

Joined: Nov 2008
From: KL
QUOTE(Imp Bron @ Dec 8 2025, 01:27 PM)
I think contractor already told next year
Higher up die2 push end of this year to push good KPI

Contractor ask they can but anything happen you tanggungjawab because you sign early release.

Client don't want to sign than this happen
*
of course la die die, this project has been delayed many times and for too long.
MR_alien
post Dec 8 2025, 02:04 PM

Mr.Alien on the loss
*******
Senior Member
3,582 posts

Joined: Oct 2007
From: everywhere in sabah



QUOTE(lorrydriverrocks @ Dec 8 2025, 01:11 PM)
U all didn't read the fine print ka ?

Keyword is LRT3 operations delayed to Dec 31 or later, there was no commitment to be ready exactly on Dec 31

https://theedgemalaysia.com/node/780900
*
yeah right
it was already all over the news and social media already and MOT didn't even made any effort to deny it laugh.gif
WinkyJr
post Dec 8 2025, 02:26 PM

Casual
***
Junior Member
433 posts

Joined: Jul 2010

QUOTE(hirano @ Dec 8 2025, 12:15 PM)
/ktard here all bising, but i bet don't even use LRT/MRT daily
*
use it since 2009 icon_idea.gif
nearlee
post Dec 8 2025, 02:35 PM

Getting Started
**
Junior Member
105 posts

Joined: May 2009
From: palaoxko
>inb4 biasa la loke7 / 69Fu Optizorb
Nearlee

joeyrm
post Dec 8 2025, 02:39 PM

Getting Started
**
Junior Member
116 posts

Joined: Jul 2005


QUOTE(lorrydriverrocks @ Dec 8 2025, 01:11 PM)
U all didn't read the fine print ka ?

Keyword is LRT3 operations delayed to Dec 31 or later, there was no commitment to be ready exactly on Dec 31

https://theedgemalaysia.com/node/780900
*
From one news, by 31st Dec.

https://www.nst.com.my/news/nation/2025/11/...ice-dec-31-loke
lopo90
post Dec 8 2025, 02:39 PM

On my way
****
Junior Member
695 posts

Joined: Nov 2010


No money letew
teehk_tee
post Dec 8 2025, 02:40 PM

ไม่เป็นไร
*******
Senior Member
5,363 posts

Joined: Apr 2005
From: กรุงเทพมหานคร BKK

QUOTE(Imp Bron @ Dec 8 2025, 01:27 PM)
I think contractor already told next year
Higher up die2 push end of this year to push good KPI

Contractor ask they can but anything happen you tanggungjawab because you sign early release.

Client don't want to sign than this happen
*
https://www.malaymail.com/news/malaysia/202...ak-links/201063

Anwar gives all ministers thumbs up in surprise midterm review, says no weak links

Stay updated on the latest news and insights. Subscribe to our newsletter here

By Syed Jaymal Zahiid
Sunday, 07 Dec 2025 1:13 PM MYT

PUTRAJAYA, Dec 7 — Prime Minister Datuk Seri Anwar Ibrahim today praised all his Cabinet members, saying they performed exceptionally well in a spontaneous midterm review recently.
diffyhelman2
post Dec 8 2025, 03:04 PM

Enthusiast
*****
Junior Member
863 posts

Joined: Apr 2019
QUOTE(ameliorate @ Dec 8 2025, 01:15 PM)
Everything all finished la. Just cannot pass final inspection. Wtf punya contractor, must be cut cost here and there, use cikai parts etc.

Done protect my beloved Tony.
*
Sounds very much like klia aero train debacle

Trains can’t run consistently at rated speed without failure/trip. If they open on Dec 31 no one will be wiser at first. But at the first breakdown will result in massive disruption not just to lrt3 but the whole network.

The risk too high for loke to push for Dec opening especially after all the flak about klia aerotrain
9m2w
post Dec 8 2025, 03:12 PM

Victoria Concordia Crescit
******
Senior Member
1,035 posts

Joined: Feb 2007


QUOTE(diffyhelman2 @ Dec 8 2025, 03:04 PM)
Sounds very much like klia aero train debacle

Trains can’t run consistently at rated speed without failure/trip. If they open on Dec 31 no one will be wiser at first. But at the first breakdown will result in massive disruption not just to lrt3 but the whole network.

The risk too high for loke to push for Dec opening especially after all the flak about klia aerotrain
*
KLIA Aerotrain more or less it was the best compromise. Further delays to the service or teething problems.

Pestech was orginally revoked the contract as they had financial difficulties but in the end reinstated (not sure if got new JV partner) as no choice, retender gonna delay it further

This one after Tokong went thru the contractors back in 2018 with a hacksaw and considering they already have sunk unrecoverable costs (wink wink) this is probably one of the side effects


version46
post Dec 8 2025, 03:13 PM

New Member
*
Junior Member
13 posts

Joined: Aug 2019


who needs trains? 4k buses also haven't reach kek.
keyibukeyi
post Dec 8 2025, 03:16 PM

Getting Started
**
Junior Member
150 posts

Joined: Oct 2009
From: Klang, Selangor D.E Status: Work Everyday
Driverless? No thanks
Iceman74
post Dec 8 2025, 03:56 PM

Regular
******
Senior Member
1,407 posts

Joined: May 2010


QUOTE(sankai80 @ Dec 8 2025, 01:03 PM)
It’s better to solve the on hands problems first before launch, better than launch first fix later attitude. Of course I’m not discounting the seeking accountability part for the delay.
*
agreed but then again.. this testing has been ongoing for some time now.

Testing should be done from A to Z and find out all the problem as a whole and fix it as a teamwork and deadline.

Hope it not
testing A to F, got problem, stop, goyang kaki and wait until part arrive or problem solving solutions
then test A to K, got problem, then stop and wait for solutions again
& continue doing this again & again

like that 2026 also cannot finish testing laugh.gif
when finished and start operation, the warranty period of the LRT train or other parts warranty already habis or start need replacement due to long time no use or under our extreme weather whistling.gif


QUOTE(blanket84 @ Dec 8 2025, 01:23 PM)
It is sarahan LGE. Mau cut cost here and there, end up everything delayed.
*
I think this cost cutting is the cause too vmad.gif

This post has been edited by Iceman74: Dec 8 2025, 04:01 PM
ye0073
post Dec 8 2025, 04:09 PM

Casual
***
Junior Member
480 posts

Joined: Sep 2004
No delay no payment coming in. Delay as long as it can, since rakyat is the one who keeps paying for the delay.
jinggothegreat
post Dec 8 2025, 04:20 PM

Casual
***
Junior Member
333 posts

Joined: Jan 2009
saw this coming lol.

no further comment. haha

 