QUOTE(knwong @ Aug 15 2023, 01:07 PM)
Thanks for this information. Very clear

Yes I'm buying direct from developer. Will follow your advise and make sure to get the schedule with ECD on this
*
You will not get the schedule coz certification is according to the Construction Progressive claim based on Architect Certification . Sometime it will be ahead, sometime it will be delayed. As soon as you received the notice, you need to clear the payment within the time frame , the date start from the Arch Certificate date.

For your info, later stage of payment will be exponential, do expect more frequent billing from 50% completion onwards.

 