News Loke: Gemas-JB ETS delayed til mid 2025

views
     
Jazted
post Mar 28 2023, 06:37 PM

On my way
****
Junior Member
542 posts

Joined: Apr 2022
QUOTE(yhtan @ Mar 28 2023, 06:27 PM)
bullshit, last year November when Wee was transport minister it was 85% progress, the balance 15% need 2 years? doh.gif
*
That mean the actual progress wasn't 85%.
Jazted
post Mar 28 2023, 07:07 PM

On my way
****
Junior Member
542 posts

Joined: Apr 2022
QUOTE(yhtan @ Mar 28 2023, 06:41 PM)
Go look at the video i post, rail track is fully done and building is almost completion
*
March 2022

Wee : it was 82.5% complete, but due to delay of covid, we can only complete by sep 2024

https://www.google.com.sg/amp/s/themalaysia...ess/amp/?espv=1


Nov 2022 (near to election)

Wee : Train was 85% complete can run by 2023.

https://www.thestar.com.my/news/nation/2022...st-ready-to-run

I think Wee was probably honest in his first statement that the plan was completing in Sep 2024. The second was just to buy vote tactics.

And if you compare the 2 report, 8 months only ran 2.5% progress. Hard to think it can be done within this year.


Jazted
post Mar 28 2023, 07:09 PM

On my way
****
Junior Member
542 posts

Joined: Apr 2022
@yhtan by the way, all the best to Johor. With the train coming + RTS. It will be a mega boost to Johor economy.

 