QUOTE(Najibaik @ Jun 12 2025, 04:25 PM)
user posted image

EcoFirst KL48 Topping Out

official launching and first spa signed on May 2023, now top the floor already  :thumbsup:
*
If you see the construction progress picture and the timeline, this project is build really really fast...

This post has been edited by UncleRoger93: Jun 12 2025, 05:13 PM
UncleRoger93
post Dec 5 2025, 11:41 AM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2025
QUOTE(Najibaik @ May 1 2024, 05:00 PM)
user posted image
user posted image
user posted image

Site progress update April
*
Last year 2024 May is Lv1
This year 2025 Dec is Lv48 topped with all MEP nearly completion...
One of the fastest project I've seen...
UncleRoger93
post Dec 5 2025, 12:18 PM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2025
QUOTE(Kelefeh @ Dec 5 2025, 11:52 AM)
on average about 3-4 floors per month
Buyers saved 1 year progressive interest

much faster compared to the projects that launch same year
sales also very good given so many units
*
If you say for the floor unit 3-4floors per month yes it's fast but relatively achievable by many developer if they want.
But this includes carpark, transfer slab, MEP and Facade and lain lain lagi
That's very fast hahaha

 