Investment KL48 @ Jalan Sungai Besi, Latest Chan Show Lin Project

views
     
Kelefeh
post Dec 5 2025, 11:31 AM

Getting Started
**
Junior Member
110 posts

Joined: Aug 2020
Another 3-4 months to VP

user posted image
user posted image
user posted image
user posted image
UncleRoger93
post Dec 5 2025, 11:41 AM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2025
QUOTE(Najibaik @ May 1 2024, 05:00 PM)
user posted image
user posted image
user posted image

Site progress update April
*
Last year 2024 May is Lv1
This year 2025 Dec is Lv48 topped with all MEP nearly completion...
One of the fastest project I've seen...
Kelefeh
post Dec 5 2025, 11:52 AM

Getting Started
**
Junior Member
110 posts

Joined: Aug 2020
QUOTE(UncleRoger93 @ Dec 5 2025, 11:41 AM)
Last year 2024 May is Lv1
This year 2025 Dec is Lv48 topped with all MEP nearly completion...
One of the fastest project I've seen...
*
on average about 3-4 floors per month
Buyers saved 1 year progressive interest

much faster compared to the projects that launch same year
sales also very good given so many units
UncleRoger93
post Dec 5 2025, 12:18 PM

Getting Started
**
Junior Member
202 posts

Joined: Jan 2025
QUOTE(Kelefeh @ Dec 5 2025, 11:52 AM)
on average about 3-4 floors per month
Buyers saved 1 year progressive interest

much faster compared to the projects that launch same year
sales also very good given so many units
*
If you say for the floor unit 3-4floors per month yes it's fast but relatively achievable by many developer if they want.
But this includes carpark, transfer slab, MEP and Facade and lain lain lagi
That's very fast hahaha
Kelefeh
post Dec 5 2025, 12:51 PM

Getting Started
**
Junior Member
110 posts

Joined: Aug 2020
QUOTE(UncleRoger93 @ Dec 5 2025, 12:18 PM)
If you say for the floor unit 3-4floors per month yes it's fast but relatively achievable by many developer if they want.
But this includes carpark, transfer slab, MEP and Facade and lain lain lagi
That's very fast hahaha
*
some developer slow progress part of the reason due to bad sales hence no funds from bank to pay contractor
For this project I think foundation was done prior official launching that's why progress is much faster

Also mainly because the china main con, not sure what tech or skill they use, really build very fast
Facilities level those trees already planted.

I think now waiting for connecting water and TNB plus paving road
Azamat_Bagatov
post Dec 5 2025, 08:36 PM

Getting Started
**
Junior Member
118 posts

Joined: Jul 2025
indeed good progress
better than many other developers or projects that launched simultaneously already
plouffle0789
post Yesterday, 11:59 AM

Regular
******
Senior Member
1,825 posts

Joined: May 2010

QUOTE(Azamat_Bagatov @ Jul 28 2025, 10:14 AM)
user posted image

user posted image

user posted image

user posted image

user posted image
*
https://kl48.com.my/



Mercure Kuala Lumpur Trion Hotel


So many projects at there


Super jam.....
Azamat_Bagatov
post Yesterday, 01:48 PM

Getting Started
**
Junior Member
118 posts

Joined: Jul 2025
QUOTE(plouffle0789 @ Dec 6 2025, 11:59 AM)
https://kl48.com.my/
Mercure Kuala Lumpur Trion Hotel
So many projects at there
Super jam.....
*
Since the whole Chan Sow Lin only got 4 condo including KL48, not really jamming now.

Mercure Hotel, Trion 1 Airbnb mostly are tourists, they not driving.

The other 2 condos Trion 2 & One Residence are low density, traffic still smooth for now

But when KL48 VP, traffic sure very syok brows.gif