Investment J. SATINE RESIDENCES / RUMAWIP @ SETAPAK, High dense project near Giant Setapak

views
     
15cm
post Apr 22 2025, 12:59 AM

Casual
***
Junior Member
422 posts

Joined: Apr 2022
anyone even dare to buy this now?
Cavatzu
post Apr 22 2025, 10:00 AM

Look at all my stars!!
*******
Senior Member
2,834 posts

Joined: Dec 2020


Looks like someone is trying to supress all media in regards to this development.
nexona88
post Apr 22 2025, 10:08 AM

The Royal Club Member
*********
All Stars
48,519 posts

Joined: Sep 2014
From: REality
QUOTE(brandonkl @ Apr 21 2025, 11:42 PM)
City Hall lifts stop-work order on parts of J. Satine condo project

New Straits Times

news@nst.com.my

KUALA LUMPUR: City Hall (DBKL) has allowed construction to resume on the Soho block, as well as Blocks A and B of the J. Satine condominium project in Wangsa Maju.

However, it said that structural repair works and foundation reinforcement must be completed on Blocks C and D before any construction activities on those blocks can proceed.
City Hall said it had received a progress report dated Feb 24 from the independent check consultant, which was prepared by a certified professional engineer.
“The report contains several recommendations and is supported by the independent engineers involved.
“It also includes verification of the building’s safety and structural stability,” it said in a statement today.
City Hall added that the recommendations had been endorsed by the independent engineers and accompanied by safety and stability certification from the structural engineers of the J. Satine development.
It has also directed the project’s consulting engineers to submit a monthly progress report and a repair work completion report, both of which must be reviewed and certified by the independent consultant at the end of each month.
The developer, Jayyid Land Sdn Bhd, has been instructed to hold engagement sessions with unit buyers and relevant agencies - including the Wangsa Maju member of Parliament’s office, the Federal Territories Department and the National Housing Department - within two weeks of the stop-work notice being lifted.
“City Hall remains committed to ensuring that all actions taken regarding the J. Satine development are guided by the principles of accountability, safety, transparency and integrity.
“City Hall will continue to closely monitor the implementation of repair works and the overall progress of the project to ensure all actions are carried out responsibly and in the best interests of all stakeholders,” it said.
On Nov 9, 2024, City Hall issued a stop-work order for the J. Satine condominium following reports of an explosion on site caused by structural issues.
An inspection revealed cracks along the shear walls, pillars, and floors in units above the eighth floor of Block C.

https://www.facebook.com/share/p/18yVcuap4o/
*
Walao...

Cable really strong ehhh...

So much issues with the project yet still gotten approval to resume work...

Well done... Bravo DBKL 👌
butthead76
post Apr 22 2025, 10:14 AM

Regular
******
Senior Member
1,495 posts

Joined: Jun 2012
Everyone knows it now. No one dare with development and developer. Foundation ko still can repair. Champion, I wonder who is the consultant on the defect report.

1 day might come down like the bangkok building.
nihility
post Apr 22 2025, 10:17 AM

Regular
******
Senior Member
1,596 posts

Joined: Sep 2021


QUOTE(nexona88 @ Apr 22 2025, 10:08 AM)
Walao...

Cable really strong ehhh...

So much issues with the project yet still gotten approval to resume work...

Well done... Bravo DBKL 👌
*
“The report contains several recommendations and is supported by the independent engineers involved.
“It also includes verification of the building’s safety and structural stability,”

The structure integrity report was prepared by independent engineers. Who are we as public to give remarks without knowing the technical details?

The rightful way as the public in my opinion, since the remedial report was ready, try to get friends in the related to industry to share their opinion on the recommendation verification. Listen to their view / opinion instead, that will be more meaningful.
icemanfx
post Apr 23 2025, 03:14 AM

20k VIP Club
*********
All Stars
21,457 posts

Joined: Jul 2012


QUOTE(nexona88 @ Apr 22 2025, 10:08 AM)
Walao...

Cable really strong ehhh...

So much issues with the project yet still gotten approval to resume work...

Well done... Bravo DBKL 👌
*
QUOTE(nihility @ Apr 22 2025, 10:17 AM)
“The report contains several recommendations and is supported by the independent engineers involved.
“It also includes verification of the building’s safety and structural stability,”

The structure integrity report was prepared by independent engineers. Who are we as public to give remarks without knowing the technical details?

The rightful way as the public in my opinion, since the remedial report was ready, try to get friends in the related to industry to share their opinion on the recommendation verification. Listen to their view / opinion instead, that will be more meaningful.
*
Most developer will declare bankrupt rather then demolish and rebuild. repair is probably the only solution for all stakeholders.

If same problem resurface after a few years, it will no longer developer, contractor or dbkl (whoever approved will probably retired by then) baby. it seems the developer have very strong cable.

This post has been edited by icemanfx: Apr 23 2025, 03:37 AM
Cavatzu
post Apr 23 2025, 03:31 AM

Look at all my stars!!
*******
Senior Member
2,834 posts

Joined: Dec 2020


Aren't people worried after what happened in Bangkok?

Can't blame people for having very low trust levels with local authorities given Putra Heights etc. Don't know what they stand for except to approve as many developments as possible to sell their land bank.

This post has been edited by Cavatzu: Apr 23 2025, 03:34 AM
butthead76
post Apr 23 2025, 07:26 AM

Regular
******
Senior Member
1,495 posts

Joined: Jun 2012
QUOTE(icemanfx @ Apr 23 2025, 03:14 AM)
Most developer will declare bankrupt rather then demolish and rebuild. repair is probably the only solution for all stakeholders.

If same problem resurface after a few years, it will no longer developer, contractor or dbkl (whoever approved will probably retired by then) baby. it seems the developer have very strong cable.
*
PV mira development had to go thru several rounds of court as PV ada cable besar.
nexona88
post Apr 23 2025, 09:20 AM

The Royal Club Member
*********
All Stars
48,519 posts

Joined: Sep 2014
From: REality
QUOTE(icemanfx @ Apr 23 2025, 03:14 AM)
Most developer will declare bankrupt rather then demolish and rebuild. repair is probably the only solution for all stakeholders.

If same problem resurface after a few years, it will no longer developer, contractor or dbkl (whoever approved will probably retired by then) baby. it seems the developer have very strong cable.
*
Either that or they use whatever route available to get things done...

So project goes on usual...
icemanfx
post Apr 23 2025, 09:30 AM

20k VIP Club
*********
All Stars
21,457 posts

Joined: Jul 2012


QUOTE(nexona88 @ Apr 23 2025, 09:20 AM)
Either that or they use whatever route available to get things done...

So project goes on usual...
*
Developer could reinstall windows and door frame, patch up and repaint crack in wall, etc. how they could remedy foundations is interesting to know.

There is s@ck@r born every minute, they believe SA and influencers. If the developer upgrade landscape and the main lobby, many will fall for it.

This post has been edited by icemanfx: Apr 23 2025, 09:35 AM
nexona88
post Apr 23 2025, 09:32 AM

The Royal Club Member
*********
All Stars
48,519 posts

Joined: Sep 2014
From: REality
QUOTE(icemanfx @ Apr 23 2025, 09:30 AM)
Developer could reinstall windows and door frame, patch up and repaint crack in wall, etc. how they could remedy foundations is interesting to know.
*
Well...

DBKL already given alprovals... Based on all the reports summited by developers....
icemanfx
post Apr 23 2025, 09:38 AM

20k VIP Club
*********
All Stars
21,457 posts

Joined: Jul 2012


QUOTE(nexona88 @ Apr 23 2025, 09:32 AM)
Well...

DBKL already given alprovals... Based on all the reports summited by developers....
*
After the highland tower incident, local authority is not liable for the consequences. Those signed the paper could be retired soon.

DragonReine
post May 3 2025, 08:08 AM

just another dog on the Internet
*******
Senior Member
2,610 posts

Joined: Aug 2011
DBKL gives nod for construction of J Satine condo to be resumed

In a filing with Bursa Malaysia, construction company TCS Group Holdings Bhd told the bourse that its subsidiary TCS Construction had received approval from DBKL for the recommencement of work on Phases 2 and 3 of the project.

“Construction work on Phase 1 would proceed once the necessary foundation strengthening is fully completed and verified by other parties,” the company said, Bernama reported.

Source: Free Malaysia Today
https://search.app/kYarf
Pixtel
post May 5 2025, 05:46 PM

Getting Started
**
Junior Member
57 posts

Joined: Jan 2015
QUOTE(DragonReine @ May 3 2025, 08:08 AM)
DBKL gives nod for construction of J Satine condo to be resumed

In a filing with Bursa Malaysia, construction company TCS Group Holdings Bhd told the bourse that its subsidiary TCS Construction had received approval from DBKL for the recommencement of work on Phases 2 and 3 of the project.

“Construction work on Phase 1 would proceed once the necessary foundation strengthening is fully completed and verified by other parties,” the company said, Bernama reported.

Source: Free Malaysia Today
https://search.app/kYarf
*
Who would wanna stay in that cracked block? 😅
BoomerangCircles
post May 5 2025, 07:14 PM

Getting Started
**
Junior Member
244 posts

Joined: Jan 2018
well.. ...
UncleRoger93
post May 5 2025, 11:13 PM

Getting Started
**
Junior Member
205 posts

Joined: Jan 2025
QUOTE(Pixtel @ May 5 2025, 05:46 PM)
Who would wanna stay in that cracked block? 😅
*
Well... I suppose all the buyers themselves?
With proper marketing and time, many new buyer's will be oblivious and continue buying and when they realize, usually it's too late...
It's the buyer's responsibilities to perform due diligence... Not Developer, not maincon, not bank...
As harsh as it may seems, it's the reality whether one like it or not



death_nite
post Jun 4 2025, 04:17 PM

Lossless Land...
*******
Senior Member
2,366 posts

Joined: Jun 2005
From: Not Here Not There...


A friend of mine shared at fb. Today got session with buyers. She said buyers were inform damage due to batu kapur and swiss cheese problem. I donno what it meant.

If cancel contract need to pay at least 60k; depending on how much bank released to developer.

Dev cant answer questions then resorted to mute and turn off the mic. No body dare enough to say it is safe after the fix being done.

This post has been edited by death_nite: Jun 4 2025, 04:18 PM
PAChamp
post Jun 4 2025, 05:13 PM

Regular
******
Senior Member
1,159 posts

Joined: Jan 2022
QUOTE(death_nite @ Jun 4 2025, 04:17 PM)
A friend of mine shared at fb. Today got session with buyers. She said buyers were inform damage due to batu kapur and swiss cheese problem. I donno what it meant.

If cancel contract need to pay at least 60k; depending on how much bank released to developer.

Dev cant answer questions then resorted to mute and turn off the mic. No body dare enough to say it is safe after the fix being done.
*
Wow looks like the foundation is limestone and there are cavities undeground. Limestone is porous and can erode over time. I am not structural engineer nor a geologist so I wonder what theose experts will say.
death_nite
post Jun 4 2025, 05:39 PM

Lossless Land...
*******
Senior Member
2,366 posts

Joined: Jun 2005
From: Not Here Not There...


QUOTE(PAChamp @ Jun 4 2025, 05:13 PM)
Wow looks like the foundation is limestone and there are cavities undeground. Limestone is porous and can erode over time. I am not structural engineer nor a geologist so I wonder what theose experts will say.
*
Yeah. She shared people were asking why developer did not do proper job working on the foundation since the building is huge and tall. No answer given. laugh.gif
hirano
post Jun 4 2025, 05:54 PM

凸(`△´#)
*******
Senior Member
3,335 posts

Joined: Nov 2007
From: Pluto


QUOTE(death_nite @ Jun 4 2025, 05:39 PM)
Yeah. She shared people were asking why developer did not do proper job working on the foundation since the building is huge and tall. No answer given. laugh.gif
*
Is your friend and other buyers gonna sue the developer beramai-ramai?