QUOTE(aniq8676 @ Feb 4 2021, 06:37 PM)
because it is part of the JENDELA project
According to TM staffs who attend my complaint, my taman falls under 'special' government project known as USP BBF (Broadband Fiberisation). It aims to convert the copper user to fibre. Maybe USP BBF was part of the JENDELA project as well.
QUOTE(powerwoot @ Feb 4 2021, 08:03 PM)
congratulations, as far as I remember you have been with streamyx for so many years and struggling demand for fibre which was the same situation as mine. I got my HSBB early this year after years of demand and complaining.
Yes, 5 or 6 years of complaining to MCMC and help@tm email. Almost every two months I wrote to them. At first, they said planning for Q3 2019 project, then Q1 2020 but due to Covid-19 pandemic the project was postponed again until 9th December last year where on that date, they finally start to lay the fibre cable to the phone pole at the back alley of my taman. But all of the port at my taman will be reserved only for existing Streamyx user. Those without Streamyx, unfortunately need to wait sometime before they 'release' the port to them. According to TM, My taman falls under 'special' project known as USP BBF (Broadband Fiberisation) - project under government funds which aims to convert copper customer to fibre. Mainly targeted to the rural and suburban areas nationwide.
QUOTE(HariszKilz @ Feb 4 2021, 10:40 PM)
Same. Looks like MCMC did the job. I just started complaining last year and they did brought Fibre into my taman. Wish I knew this earlier. Anyway, how long would they activate your DP for installation ? Mine is already a month after finish installing all the Fibre component in my taman (DP, FDC, Joint) and until now still not activated yet. I already reached TM for the status and speed up the process since this WFH and people need fast internet to work and they said they will acknowledge it and until now, no news like 2 weeks now. I asked TMPoint and they said the guy who supposed to verify the DP etc still not showing up until today. What a joke sia this TM in my area. Haizzz
Project timeline based on my observation:
9 December 2020 - Contractor start to lay the fibre cable to my taman.
Early January 2021 - They finally 'bury' all of the cable to the main manhole at the entrance of taman.
Mid January 2021 - Black box FDP was installed.
End of January 2021 - FDP and pole labelling. They tied up the fibre cable to the loop shape as well.
1 February 2021 - received the call from agent that said my taman has been in service for unifi and they will submit my application to TM.
2 February 2021 - received the SMS from TM that stated that my unifi will be installed on the next day, 3rd February on afternoon session.

Thankfully, I was scheduled to WFH on 3rd february. If not need to ask for emergency leave.
3 February 2021 @ 5.00pm - The technician came to install my Unifi. The second installation on that day for my taman. Installation was FOC due to standard installation only.
Overall, it takes about 2 months for the project to be settled.
This post has been edited by AjkR06: Feb 5 2021, 08:57 AM