Hi all,

I have a question here, i have friends who working in renovation field which most office require networking service. My friend ask me whether I'm interested or not. But I'm thinking that what is the things/area that I need to be concern of? or what are the things that I need beware of?

Those who have experience can give me some tips & guide. Or how should I prepare the list? Or how the rate is charged? Is this job very troublesome?


Thank you veri much@.
kakarocht
post Aug 13 2007, 05:16 PM

Hibernate Time.............
*******
Senior Member
3,254 posts

Joined: Feb 2006
From: Tekken - Mishima Corps.
if laying the cabling then it's troublesome... laugh.gif
mwkh_hope
post Aug 14 2007, 09:17 AM

Casual
***
Junior Member
406 posts

Joined: Jun 2005
From: a small location in earth.


i think mostly laying cable part will be before the partition wall is up. So i think shouldn't be a big problem.
joshua963
post Aug 19 2007, 03:38 AM

Casual
***
Junior Member
353 posts

Joined: Oct 2006
From: kLwithaG


i think per point is around 80-100.. Because the standard rate for electical plug point is around 80 too.. so both should be around the same... but to be extra sure, try checking with ur supplier or electrical shops the price for cat5e cable, wall mounted socket, conduit/flexsible pipe n patch panel ( if ur using an i.t rack or something to have the router all fixed).. From there u should be able to get a rough idea of the actual costing of the material.. Once u got that, add another RM 50 for labour charge..n That should be the price per point.. smile.gif
mwkh_hope
post Aug 24 2007, 02:28 AM

Casual
***
Junior Member
406 posts

Joined: Jun 2005
From: a small location in earth.


QUOTE(joshua963 @ Aug 19 2007, 03:38 AM)
i think per point is around 80-100.. Because the standard rate for electical plug point is around 80 too.. so both should be around the same... but to be extra sure, try checking with ur supplier or electrical shops the price for cat5e cable, wall mounted socket, conduit/flexsible pipe n patch panel ( if ur using an i.t rack or something to have the router all fixed).. From there u should be able to get a rough idea of the actual costing of the material.. Once u got that, add another RM 50 for labour charge..n That should be the price per point.. smile.gif
*
Thank you for your advice, Joshua963. This can help me on preparing price list & quotation. Thank you rclxms.gif biggrin.gif

 