Hi,
What should we do if developer is taking too long to complete the defects? It was reported end Dec 2019, til today, still not completed. They even asked to do a joint inspection to close the defects, but now cancelled cos they said cannot make it in time. 2 months plus and still not ready
|
|
|
|
|
|
TSjian5481
|
Mar 10 2020, 06:36 PM
|
|
QUOTE(CRaider2 @ Mar 10 2020, 06:34 PM) Look back at your SPA and check if you are allowed to claim LAD (Liquidated Ascertained Damages). Best to put a letter in writing to the developer on their failure to complete the job according to their SLA. LAD clause also applies for defect rectification after VP?
|
|
|
|
|