What to do if defect not fixed within 30 days?, Newly VP, within DLP
|
CRaider2
|
Mar 10 2020, 06:34 PM
|
Getting Started

|
Look back at your SPA and check if you are allowed to claim LAD (Liquidated Ascertained Damages). Best to put a letter in writing to the developer on their failure to complete the job according to their SLA.
|
|
|
|
|
|
CRaider2
|
Mar 11 2020, 11:03 PM
|
Getting Started

|
It really depends on the wording of your SPA. Taking VP does not mean the end of the developers responsibility and liability. You can give them ample time to fix at their cost or you pay to fix it and claim back the costs.
|
|
|
|
|