Hi everyone I decided to book a unit with EcoWorld on one of their high rise projects. The package that comes with my unit has multiple fittings like light fixtures and furniture like sofa and kitchen counter.
The SA gave me this timeline
Loan submission & approval - approx 1 month
Bank drawdown - approx 2 months
VP handover - approx 1 month
Defect checking - approx 1 month
Fitting & furnishing- approx 3-5 months
*but for fitting & furnishing, is estimated about this time frame.
Why VP handover before fitting and furnishing? Then like that if the fitting and furnishing got issue then the defect checking period over, I won't be able to claim?
I'm guessing it should be the unit is fully completed then VP? Thanks for any help.
it sound strange, normally when VP, everything must be there.The SA gave me this timeline
Loan submission & approval - approx 1 month
Bank drawdown - approx 2 months
VP handover - approx 1 month
Defect checking - approx 1 month
Fitting & furnishing- approx 3-5 months
*but for fitting & furnishing, is estimated about this time frame.
Why VP handover before fitting and furnishing? Then like that if the fitting and furnishing got issue then the defect checking period over, I won't be able to claim?
I'm guessing it should be the unit is fully completed then VP? Thanks for any help.