> LBU kicked out from Pan Borneo highway project, state JKR to fully take over, cut cost

views
     
TSlagista
post Oct 4 2019, 05:08 PM, updated 7y ago

New Member
*
Newbie
25 posts

Joined: Oct 2018


good move by federal Works Ministry get rid of middle man, reduce costs! thumbup.gif

user posted image

LBU role in Sarawak Pan Borneo Highway axed
1 Oct 2019 SoS
QUOTE
KUCHING: Lebuhraya Borneo Utara Sdn Bhd (LBU), whose role as the project delivery partner (PDP) of Sarawak Pan Borneo Highway project has been axed, is given five months to hand over the project to Sarawak Public Works Department (JKR).

The handover date is February 2020, according to Works Minister Batu Bian’s special officer for the ministry’s projects in Sarawak, See Chee How.

LBU confirmed with StarBiz that it received the PDP termination letter on Sept 20.

“We have to novate all the main contractors (of the 10 work packages) to JKR. There will be no change to their agreements, ” said See in his presentation on Pan Borneo Highway – a game changer for Sarawak infrastructure at the 2019 Sarawak Investment and Business Summit here.

LBU, which is linked to Sarawak tycoon Tan Sri Bustari Yusof, was awarded the contract (phase 1) valued at about RM16.49bil in 2015. One of the 11 work packages involving total length of about 749km from southern Sarawak to the north in Miri, has been completed.

‘Cabinet agrees to remove PDP of Pan Borneo Sarawak’
6 Sep 2019 SoS
QUOTE
While construction works are underway, the highway project continues to be under scrutiny as the Pakatan Harapan-led government remains laser-focused on cost-cutting.

Baru was earlier reported as saying that his ministry can bring down the project’s cost should the federal government take over from the PDP.

This is as a fee of 5.5% of the project cost must be paid to the PDP under the contract agreement. Given the RM16.49 billion price tag, this means that the PDP model for the Pan Borneo Highway in Sarawak would have cost the government some RM907 million.  shocking.gif  shakehead.gif

PDP contractors usually earn a certain percentage of a project’s cost, but do not have to bear the full brunt of cost overruns and delays, as compared with the turnkey model, in which the project cost is fixed from the beginning.

PH govt always sayang rakyat cut down wastage by lanunku cronies thumbsup.gif
wankongyew M4A1
TSlagista
post Oct 4 2019, 05:10 PM

New Member
*
Newbie
25 posts

Joined: Oct 2018


Bustari Brothers Booted Out of pan borneo project
22 Mar 2019
https://forum.lowyat.net/topic/4755524
and85rew
post Oct 4 2019, 05:12 PM

Red Devil
*****
Senior Member
877 posts

Joined: May 2006
From: Kuching


Haha eat that
bliztnull
post Oct 4 2019, 05:15 PM

New Member
*
Newbie
4 posts

Joined: Jun 2013
Good, now if project delay, ppls know who's to blame laugh.gif
Jasonist
post Oct 4 2019, 05:16 PM

Oldfag
******
Senior Member
1,176 posts

Joined: May 2006
From: Memesia



tahap songlap melampau
TSlagista
post Oct 4 2019, 05:16 PM

New Member
*
Newbie
25 posts

Joined: Oct 2018


QUOTE(and85rew @ Oct 4 2019, 05:12 PM)
Haha eat that
*
Only the top middle man removed, the contractors are still the same n works continue as usual...

Pan Borneo Sarawak: PDP officially terminated, construction to continue as usual, says Baru Bian
27 Sep 2019 SoS

...Despite the termination, he said that all the 11 work package contracts (WPCs) for the 786.41km highway on the Sarawak side would be continued by previously appointed contractors.

“Let me emphasise, all the main contractors for the WPCs will still be novated, they will still go on. No issue with that.

“As far as I am concerned, once LBU is terminated, all the WPCs should be novated, that’s the idea with this project,” he told reporters when met after chairing a joint Sarawak and Federal Government Action Council meeting here, today.
xplodingplastix
post Oct 4 2019, 05:17 PM

Getting Started
**
Junior Member
224 posts

Joined: Oct 2010
From: Cyberjaya.SK.Puchong


thats 20mil+/km perghhh LJ
TSlagista
post Oct 4 2019, 05:18 PM

New Member
*
Newbie
25 posts

Joined: Oct 2018


QUOTE(bliztnull @ Oct 4 2019, 05:15 PM)
Good, now if project delay, ppls know who's to blame  laugh.gif
*
Sabah section of Pan Borneo also same crap, middle man removed...

SoS

...On March 21, The Edge Financial Daily, quoting sources, broke the news that the federal government cancelled the PDP model for the Sabah portion of the highway project, in favour of the turnkey contractor model.

MMC Corp Bhd had later confirmed that Borneo Highway PDP Sdn Bhd (BHP) had on April 22 received a notification from the government on the termination of its PDP agreement.

BHP is 40% owned a joint venture between UEM Group Bhd and MMC Corp Bhd — UEM MMC Joint Venture Sdn Bhd — which gives MMC an effective 20% stake in BHP. The remainder 60% in BHP is owned Sabah-based Warisan Tarang Construction Sdn Bhd, which was said to be connected to Sabah Umno and former chief minister Tan Sri Musa Aman.
gogocan
post Oct 4 2019, 05:21 PM

Casual
***
Junior Member
485 posts

Joined: Dec 2013
This bustari very close friend with najib? Time for LHDN to move some muscles
SUSBillCollector
post Oct 4 2019, 05:22 PM

Enthusiast
*****
Junior Member
818 posts

Joined: Jul 2019
Finally the anti-songlap measures have reached that part of the country.
Sycamore
post Oct 4 2019, 05:28 PM

Casual
***
Junior Member
334 posts

Joined: Jun 2015
From: underneath the grove of sycamore
This one known crony.

But i thought Najib said he has no crony? Malaysian is his cronies?
lucifer_666
post Oct 4 2019, 05:39 PM

Getting Started
**
Junior Member
234 posts

Joined: Oct 2008


QUOTE(gogocan @ Oct 4 2019, 05:21 PM)
This bustari very close friend with najib? Time for LHDN to move some muscles
*
Brother of Fadilah Yusoff. MP for Petra Jaya.
xtrabite
post Oct 4 2019, 06:10 PM

Getting Started
**
Junior Member
181 posts

Joined: Mar 2009
From: Pengu world


Good job.. keep it up..
and85rew
post Oct 4 2019, 10:50 PM

Red Devil
*****
Senior Member
877 posts

Joined: May 2006
From: Kuching


QUOTE(lagista @ Oct 4 2019, 05:16 PM)
Only the top middle man removed, the contractors are still the same n works continue as usual...

Pan Borneo Sarawak: PDP officially terminated, construction to continue as usual, says Baru Bian
27 Sep 2019 SoS

...Despite the termination, he said that all the 11 work package contracts (WPCs) for the 786.41km highway on the Sarawak side would be continued by previously appointed contractors.

“Let me emphasise, all the main contractors for the WPCs will still be novated, they will still go on. No issue with that.

“As far as I am concerned, once LBU is terminated, all the WPCs should be novated, that’s the idea with this project,” he told reporters when met after chairing a joint Sarawak and Federal Government Action Council meeting here, today.
*
i mean the pdp/crony tongue.gif
TSlagista
post Oct 5 2019, 09:55 AM

New Member
*
Newbie
25 posts

Joined: Oct 2018


QUOTE(xplodingplastix @ Oct 4 2019, 05:17 PM)
thats 20mil+/km perghhh LJ
*
RM16 billion projek... burrppp kenyanggg
Emily Ratajkowski
post Oct 5 2019, 09:59 AM

Casual
***
Junior Member
444 posts

Joined: Nov 2014
Walau eh. They really robbing us. Jibai corruption really destroys a country.
ikankering
post Oct 5 2019, 10:04 AM

New Member
*
Newbie
42 posts

Joined: Jan 2017
oh my..
AyamBlend
post Oct 5 2019, 10:18 AM

New Member
*
Junior Member
27 posts

Joined: Nov 2011
Dealing with msia contract u know

The guy who actually do the job get 1% profit as example, but one introducer outnof nowhere come out tell u i need 3% only.
Then top introducer 10% do nth but delay payment and ask for more money
SUSAlexcky3
post Oct 5 2019, 10:20 AM

New Member
*
Junior Member
14 posts

Joined: Apr 2019
Lbu is a bunch of leech according to my client who work for pan borneo project