 Should I sue them for, late delivery vacant possession

views
     
TSHAoCHa
post Apr 26 2019, 11:36 PM, updated 7y ago

Getting Started
**
Junior Member
52 posts

Joined: Mar 2012


Hi all Sifus

I bought a house which include a free renovation package.
SPA signed 3 months ago, and loan already draw down early of this month, but I cannot get the key yet because the renovation work is not done yet.

In this situation, do I have the right to claim late interest from the developer?
If so, how do i proceed? What document required?

All sifu please help. cry.gif

Attached is my reno package & SPA contracts

Attached File  reno___SPA_2.pdf ( 4.58mb ) Number of downloads: 85


This post has been edited by HAoCHa: Apr 26 2019, 11:42 PM
jimmyng
post Apr 27 2019, 12:37 PM

Getting Started
**
Junior Member
221 posts

Joined: May 2017
From: Negeri Sembilan


when you signed the SPA, you use your own lawyer or developer's?
If you used yours, then you can consult him.
If not, usually developer's lawyer will write a contract that advantageous to the developer.

My advise, get a lawyer to help you check.
Or maybe there's any lawyer in this forum that can help out
TSHAoCHa
post Apr 27 2019, 12:44 PM

Getting Started
**
Junior Member
52 posts

Joined: Mar 2012


QUOTE(jimmyng @ Apr 27 2019, 12:37 PM)
when you signed the SPA, you use your own lawyer or developer's?
If you used yours, then you can consult him.
If not, usually developer's lawyer will write a contract that advantageous to the developer.

My advise, get a lawyer to help you check.
Or maybe there's any lawyer in this forum that can help out
*
I use developer lawyer as they free legal fee.
And yes, they word the contract favor the developer... doh.gif
hanhanhan
post Apr 27 2019, 03:34 PM

(͡ ͡° ͜ つ ͡͡°)
******
Senior Member
1,205 posts

Joined: Oct 2006
From: Kuala Lumpur


QUOTE(HAoCHa @ Apr 26 2019, 11:36 PM)
Hi all Sifus

I bought a house which include a free renovation package.
SPA signed 3 months ago, and loan already draw down early of this month, but I cannot get the key yet because the renovation work is not done yet.

In this situation, do I have the right to claim late interest from the developer?
If so, how do i proceed? What document required?

All sifu please help.  cry.gif

Attached is my reno package & SPA contracts

Attached File  reno___SPA_2.pdf ( 4.58mb ) Number of downloads: 85

*
Was all the things in the appendix in the property upon handing over vacant possession?
TSHAoCHa
post Apr 27 2019, 03:55 PM

Getting Started
**
Junior Member
52 posts

Joined: Mar 2012


QUOTE(hanhanhan @ Apr 27 2019, 03:34 PM)
Was all the things in the appendix in the property upon handing over vacant possession?
*
im not yet getting the key, still under renovation, haven't even check defects yet.


 