 How do you interpret "Ready for Connection"

views
     
kimzee
post Nov 8 2018, 12:05 PM

Casual
***
Junior Member
411 posts

Joined: Jan 2018
QUOTE(ulala2 @ Nov 8 2018, 10:50 AM)
In standard residences property SPA (Schedule H),
under Clause 27 Manner of Delivery of Vacant Possession,
Item ©,
- water and electricity supply are ready for connection to the said Parcel

Also under clause 1(k), the definition of "ready for connection" means

- means electrical points and water fittings and fixtures in the said Parcel have been installed by the Developer and are fully functional and supply is available for tapping into individual parcels.

Question:[U]

1) Pursuant to Clause 1(k), does this mean that the developer need to install the water meter and electricity meter before issue vacant possession?

2) As we aware, water meter installed by Syabas, electricity meter installed by TNB, any delay in the meter installation by these both parties also under Developer obligation?

3) Can Developer still issue vacant possession without water and electricity meter installed?

Please advise.
TQ
*
I am no lawyer but from my interpretation it means your parcel is "ready for connection" when all the relevant water piping and electrical cable are connect to the common conduit and routed to the main duct where it will be connected to Public Utilities Provider. Hence developers are not responsible for the meters.

If you have bought a unit, can just clarify with your S&P lawyer.

 