In standard residences property SPA (Schedule H),
under Clause 27 Manner of Delivery of Vacant Possession,
Item ©,
- water and electricity supply are ready for connection to the said Parcel
Also under clause 1(k), the definition of "ready for connection" means
- means electrical points and water fittings and fixtures in the said Parcel have been installed by the Developer and are fully functional and supply is available for tapping into individual parcels.
Question:[U]
1) Pursuant to Clause 1(k), does this mean that the developer need to install the water meter and electricity meter before issue vacant possession?
2) As we aware, water meter installed by Syabas, electricity meter installed by TNB, any delay in the meter installation by these both parties also under Developer obligation?
3) Can Developer still issue vacant possession without water and electricity meter installed?
Please advise.
TQ
How do you interpret "Ready for Connection"