Hi all,
i am in need of some advise - more of your experience and attending to this from a legal point of view
i submitted my defect list in February and until now, they are not completing the job. latest promise was on may 25th that it will take 2 week....and i've just visited the place and the flooring has been removed....effectively another 2 weeks delay
in the S&P, there is a clause of 30 days completion of defect submission hence i am considering legal action to get some compensation from this large and well known developer.
I've been renting a house and plan to move in March but until now, i have to serve both rental and loan repayment to the bank. i am struggling and feeling victimized by this action in delaying the remediation of the defects.
please help kind sir's and ma'am's to advise how do i best position this to my best advantage againts this developer
HELP - Developer taking too long to fix defect