QUOTE(madman20 @ Mar 11 2019, 05:30 PM)
Hi guys..first time home buyer here..I'm in a situation and need some advice from experts here..here's the timeline
Developer says LAD is up to 23rd January 2019 as per VP letter and not based on the day they sent out the VP letter (2nd/7th March 2019 - number not so clear between 2 or 7)
They asked me to write in..and even so that's not guaranteed to get LAD up to the date the letter sent out

Which project is this? Is this a schedule H development? If yes you can bring to tribunal. | 11th November 2015 : | Signed Sales & Purchase Agreement |
| 11th November 2018 : | Actual Vacant Possession Date. No Vacant Possession Letter from Developer. |
| 23rd January 2019 : | Developer issues Vacant Possession letter. |
| 19th February 2019 : | Bank releases 100% Payment to developer. |
| 2nd/7th March 2019 : | Vacant Possession posted (date on envelope stamping), non-registered mail. |
| 8th March 2019 : | Vacant Possession received at mailing address |
| 11th March 2019 : | Visit developer’s office to pay Service Charge, TNB and SYABAS Deposits. Parcel inspection date set to 23rd March 2019, 9am. |
Developer says LAD is up to 23rd January 2019 as per VP letter and not based on the day they sent out the VP letter (2nd/7th March 2019 - number not so clear between 2 or 7)
They asked me to write in..and even so that's not guaranteed to get LAD up to the date the letter sent out