Investment THE TROPIKA RESIDENCES @ BUKIT JALIL, The Ever Greens of Par Way
|
storky20
|
Mar 7 2020, 11:38 AM
|
Getting Started

|
Any other owners that got the revised floor plan message know where exactly is the refuse chamber located? I’m in a unit where there’s now a door facing my unit and if it’s the refuse chamber... zzz.
|
|
|
|
|
|
storky20
|
Nov 25 2020, 12:41 PM
|
Getting Started

|
Anyone with Type B got a recent email on design changes? Looks like they're (1) increasing the size of toilet door and (2) changing the design of the kitchen window to a 'sliding window'.
Hmmm not bad.
|
|
|
|
|
|
storky20
|
Nov 25 2020, 05:42 PM
|
Getting Started

|
QUOTE(harisons @ Nov 25 2020, 05:04 PM)  but looking at the layout, i don't think the window width at kitchen at the moment has sufficient space to do a sliding window, said 600mm width (so each panel 300mm?) unless it is sliding to top. also the toilet door, let say if they are going to increase the door width, this will affect the turning radius as it will hit the basin. unless they r increase the door width for master bath / bath 2. Correct, the toilet door will be wider (from 700mm to 900mm) which will make it feel a bit more 'tight' when turning also. From the diagram provided, it's for Master/Bath 2/Bath 3. For the kitchen window, no example of the window was provided but yeah, I assume it's slide sideways partially instead of the full 300mm radius.
|
|
|
|
|
|
storky20
|
Nov 27 2020, 06:51 PM
|
Getting Started

|
QUOTE(srsue @ Nov 27 2020, 06:36 PM) I didnt receive email on this Maybe you're a different tower? Mine's Tower A which might have a slightly different spec from the rest considering it's 'older'. Possible there's revisions done since then for the newer towers.
|
|
|
|
|
|
storky20
|
Nov 28 2020, 11:08 AM
|
Getting Started

|
QUOTE(Suzuki688 @ Nov 28 2020, 08:01 AM) If you visit the sales gallery recently for Type C. You will be able to noticed the design for master bedroom toilet has been changed and enlarged.. Not sure it will apply for Block B C and D only or A as well I think should be standard across the blocks. Signed late last year and got few revisions since then that have to be submitted to the lawyers officer for acknowledgement. All good. Better than nothing haha.
|
|
|
|
|
|
storky20
|
Mar 27 2021, 02:49 PM
|
Getting Started

|
QUOTE(wrl1992 @ Mar 27 2021, 06:52 AM) Looks like Berjaya started selling Tower C Saw the ads on Facebook advertising Tower C too
|
|
|
|
|
|
storky20
|
Oct 29 2022, 09:51 AM
|
Getting Started

|
Looks like the Starbucks and Baskin Robbins is up. Can’t wait to see the rest.
|
|
|
|
|
|
storky20
|
Nov 22 2022, 04:13 PM
|
Getting Started

|
Starbucks - open Anytime Fitness - open Baskin Robbins - open Oomph Cafe - open Watsons - opening soon (reno complete). Jaya Grocer - opening this weekend (24th Nov). Kam Kee Cafe - reno ongoing.
Just some things I saw last weekend.
|
|
|
|
|
|
storky20
|
Mar 25 2023, 02:40 PM
|
Getting Started

|
QUOTE(rumahwip @ Feb 20 2023, 01:01 PM) Moved to Q2'2024 bro... source
|
|
|
|
|
|
storky20
|
May 5 2024, 06:45 PM
|
Getting Started

|
Wondering when is VP also, initially saw news say it's gonna be Q2'24. Loan also billed all the way till pre-VP stage.
Have emailed, called, but sales seems to not have any updates except Q2'24 delivery.
Wonder what's up hmm.
|
|
|
|
|
|
storky20
|
May 12 2024, 09:23 PM
|
Getting Started

|
QUOTE(Babizz @ May 8 2024, 03:30 PM) There is already a telegram group with tonnes of discussion. Visited last weekend. Pls dont bliv any date in the group. Would appreciate the link to the group as well. DM?
|
|
|
|
|